Additional payment due to rising construction costs: what are the options?

Cobouw is full of stories about it. The prices of construction materials are soaring. At the time of writing, since January this year, prices for timber and sheet materials have risen by 20%, steel prices by no less than 77%, oil (relevant to the price of bitumen) by 36% and copper by 31%. Price rises are nothing new in themselves. For many years, the law, the UAV 2012 and the UAV-GC 2005 have all included provisions for substantial price rises. Given how topical these price rises are now, there is every reason to take a closer look at those provisions.
Cost-increasing circumstances
In the event of substantial price rises, both the law and the UAV 2012 entitle the contractor, provided certain requirements are met, to (partial) compensation for these additional costs. The conditions are that the contractor could not have foreseen the price rises when the construction contract was concluded, and that the price rises substantially increase the cost of the works.
In the past, when steel prices suddenly and unexpectedly rose sharply, contractors successfully invoked these so-called cost-increasing circumstances. Case law from that time established, among other things, that neither a fixed-price clause nor a risk-sharing arrangement prevents a contractor from invoking cost-increasing circumstances. These are considered to apply to ‘normal’ price rises, but not to abnormal ones.
Significance threshold
A contractor can claim additional payment for cost-increasing circumstances only if the increase in costs is substantial. Unfortunately, there is no clear rule for determining when this is the case. A 2016 ruling by the Council of Arbitration for the Building Industry appears to offer some guidance in the form of a rule of thumb: an increase in costs of more than 5% of the total contract sum would be substantial. However, there is also case law rejecting such a rule of thumb. Whether the increase in costs is substantial depends on the circumstances of the case. This is an open-ended standard and, unfortunately, offers little guidance in practice.
Business risk
It should also be borne in mind that the Council of Arbitration always considers the extent to which the contractor should have anticipated a certain degree of price rises. This is known as business risk: the proportion of the increase in costs that the contractor must bear itself. Note that in the cases mentioned above concerning the rise in steel prices, this risk was regularly assessed at between 10% and 20% of the increase in costs.

Unforeseen
Finally, the cost-increasing circumstances must be unforeseen. This may be arguable for contracts awarded before the recent sharp price rises, although prices had already risen quite substantially after the credit crisis. It will be much harder to rely on the provisions referred to above for contracts being awarded now. In light of the sharp price rises of recent months, further rises may be considered foreseeable. In that case, a claim based on cost-increasing circumstances will not succeed.
Duty to warn
Both the law and the UAV 2012 require the contractor to warn the client of the cost-increasing circumstances as soon as possible. Failure to do so precludes a successful claim based on cost-increasing circumstances. The rationale behind this provision is that the client must be able to adjust the order in order to limit its costs.
UAV-GC 2005
Under the UAV-GC 2005, the contractor is entitled to compensation for costs if an unforeseen circumstance arises that is such that the contract cannot remain in force unchanged. The drafters of the UAV-GC drew on the statutory provisions governing unforeseen circumstances. This is generally considered to be a very strict test. Successful claims under this provision are virtually unheard of, and it is harder to rely on than the so-called cost-increasing circumstances provisions in the law and the UAV 2012.
Finally
Successfully claiming additional payment because of rising construction costs is not easy. But the provisions in the law and the UAV 2012 are there for a reason, and contractors have successfully relied on them in the past. In the current climate, it may be worth checking whether the main requirements for a claim for additional payment are met. R.J. Kwaak, construction law solicitor at Construct Advocaten
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeViable projects and strong collaboration
- SubjectNews
- CompanyConstruct Advocaten