A high-voltage substation as a ‘construction kit’

Text Suzanne van Gaale Images Mobilis / TenneT

Artist impression van het gehele gebied waar het hoogspanningsstation wordt gebouwd.
Artist impression van het gehele gebied waar het hoogspanningsstation wordt gebouwd.

Optimum construction speed and quality 

The new 380 kV high-voltage substation near Tilburg is being built by Samenwerking Croonwolter&dros, Mobilis (SC&M). Work began at the start of this year. To optimise the project schedule, SC&M is using Mobriq, a modular design developed in-house that makes extensive use of prefabricated components. Project directors Jochem Mol and Rik van Opdorp explain their approach to the partnership and construction work.

“In broad terms, we were commissioned to engineer, build and deliver the entire 380 kV substation ready for operation,” Rik explains. “The new high-voltage substation comprises thirteen bays and three transformers, which convert electricity from 380 kV to 150 kV. A substantial amount of construction work is needed to make this possible.” Jochem adds: “Based on TenneT’s preliminary design, SC&M is responsible for developing the final design and detailed design. We will deliver the project based on that detailed design. In the first phase, Strukton and Gubbels prepared the site for construction. We are picking up from there in the next phase. We will start by installing bored piles and foundations. Nothing will be driven into the ground, everything will be drilled because of the badger sett. We will then install the bay foundations using the Mobriq system. This modular system consists of precast beams that form a pattern, allowing us to build bays quickly and efficiently.”

The new high-voltage substation comprises thirteen bays and three transformers, which convert electricity from 380 kV to 150 kV.

Modular construction with Mobriq

The Mobriq system was ‘born’ out of the desire and urgent need to build ‘differently’. The new high-voltage substation near Tilburg is part of TenneT’s EU303 programme, a major programme to expand and upgrade around 360 high-voltage substations in the Netherlands. Efficient construction is essential to deliver this programme. Rik explains: “SC&M developed Mobriq as a modular concept that significantly shortens both the design process and the conversion work on site. It is a modular design that uses a large number of prefabricated components prepared in the factory. At its core are two types of concrete beam, with standard upstands and standard spacings. A crane can lay one layer of Mobriq beams for two bays in a day. We developed the system based on lessons learned from our previous projects for TenneT. We knew exactly where the bottlenecks were, so we set to work on them, resulting in the Mobriq system. Mobriq is one of the reasons we are on track to meet the tight schedule in Tilburg.”

Right through to testing

Rik explains: “As well as installing the bay foundations, we are carrying out the concrete work for the lightning masts and the basement pits for the transformer and reactor cells. Once the initial civil engineering work is complete, we will install the steelwork and high-voltage components, followed by the primary components. We can then move on to the control and power supply systems, or, in simple terms, pulling and connecting cables. The final stage is testing and commissioning the substation. In parallel, we are building three transformer and reactor cells so that they are ready for the transformers to be installed. We will install the bay control buildings, a central services building housing all the equipment used to control the substation, and three transformers. Once the work is complete in 2026, we will put up a fence. Another point worth mentioning is that we are constructing a swale to collect rainwater at the substation. The water can then infiltrate into the ground on site. We are laying grass pavers made from recycled plastic in the substation. The grass grows in small squares, so it stays shorter than normal and provides a stable surface for safely walking over to inspect components.”

Expanded collaboration

Croonwolter&dros and Mobilis are working together on this project. Jochem explains: “We have set up a single project organisation, known informally as the Koepel. It brings together the right people from both organisations, who have jointly developed the design through to detailed design. The two parties are now working across disciplines on the basis of this design, with project management also handled as an integrated team. SC&M has been working for TenneT for the past five years. But this is the first new-build 380 kV substation that we have designed and built entirely from start to finish, covering civil engineering, primary, secondary and tertiary systems. What’s great about working together is that we all give it our best, communicate openly and take the time to celebrate our successes.”  

Have a business enquiry for Mobilis? Get in touch

Wie aan 380 kV hoogspanningsstation Tilburg werkte

  1. Collaboration Croonwolter&dros: MobilisCroonwolter&drosMentioned in Preparation for construction of Tilburg 380 kV substation now getting under way
  2. Collaboration Croonwolter&dros: MobilisMobilisMentioned in Preparation for construction of Tilburg 380 kV substation now getting under way
  3. engineering and consultancy firmAntea GroupMentioned in Preparation for construction of Tilburg 380 kV substation now getting under way
  4. prepared for constructionStruktonIn this story
  5. prepared for constructionGubbelsIn this story
  6. clientTenneTMentioned in Antea Group provided consultancy services for Tilburg high-voltage substation
  7. earthworks and remediation partnerGubbels Infra & MilieuMentioned in Strukton and Gubbels lay the foundations for Tilburg high-voltage substation

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • Project380 kV high-voltage substation Tilburg
  • ThemeMaterials and techniques for infrastructure
  • SubjectNews
  • CompanyStrukton Civiel
  • CompanyGubbels
  • CompanyMobilis
  • CompanyCroonwolter&dros
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.