Pilz delivers new control centre for movable bridges
Text Susan Peek Beeld Provincie Zuid-Holland, Pilz

In an earlier article in GWW, we took an in-depth look at the strategic partnership between the Province of South Holland and Pilz Nederland. While that article focused on standard control software for bridges and locks, Pilz has also been working in parallel on a new control centre for the movable bridges in the Province of
South Holland. Ricardo Duijser, project engineer at Pilz Nederland, and Coen Veldhuis,
senior adviser/project manager at the Province of South Holland (PZH), tell us more.
“There are currently three control centres in the Province of South Holland,” says Ricardo. “De Waard in Leiden, together with the Leidschendam control centre, operates the bridges west of the Alphen aan den Rijn to Rotterdam line. Then there is Steekterpoort, a large, modern control centre in Alphen aan den Rijn. It remotely controls the bridges in the area around Alphen aan den Rijn.”

New control centre
To ensure the smooth, safe and reliable passage of commercial and recreational shipping in the future, it was decided to combine the Leidschendam and De Waard control centres in a single new centre. This will be located in the Centrale Koningspoort at the Provincial Hall in The Hague. “The great thing about the changes Pilz is making to the existing software is that every bridge in the Province of South Holland will be fully automated and controllable from either control centre,” says Coen. “That gives us much greater flexibility.” Ricardo explains that the number of operator positions will increase to 24 and that Pilz is working to further optimise the software so that the data flow is better distributed across the available PLCs.

Training centre
“A particularly unusual feature is that 6 of the 24 operator positions must also be available for training,” says Ricardo. “PZH’s training centre is currently in Gouda, but it will also move to the Provincial Hall. These 6 positions are in a separate room and must be switchable between operational and training use, and vice versa.”

New implementation means extensive testing
“A new control centre with an adapted control concept is no small undertaking,” says Coen. “So it is essential to test everything thoroughly: we need to demonstrate that it works as PZH wants and as Pilz has designed it. In fact, I want a testing process, not a construction process. Fortunately, that is also how Pilz works.” Ricardo says: “We have brought the entire control system forward to align with the adapted operating concept, so we can start implementing and testing now, before bringing all the components together later. This will allow us to demonstrate that the adapted concept we have devised for the communications works.” Only then will everything be installed in PZH’s test setup. “PZH, Pilz, which is responsible for the control system, CGI, which is responsible for the Graphical User Interface, and the network manager are working closely together on the technical design to ensure everything functions optimally.” Coen explains that coordinating everything requires quite a complex schedule. “It helps that Pilz is so cooperative and works with us to make sure everything runs smoothly.”

Strategic partnership
“The most important thing about developing software is how it is used,” Coen continues. “It simply has to work well, and that is what I find with Pilz. They are able to think outside the box, challenge us and themselves, look ahead and work with us. As the person who comes up with a particular functionality, I can tell Pilz what they need to consider. They take that on board, incorporating our wishes, requirements and principles, adding their own expertise and getting to work. Along the way, they ask searching, challenging questions that benefit the process and the end result.” Ricardo adds: “For us, automation is not an end in itself, but supports the task at hand. In this case, it means operating bridges remotely with fewer people.” Coen concludes: “They take every aspect into account as part of the process, including the quality of the solution, as well as time, budget, information and documentation. In my view, that is the strength of Pilz and its strategic partnership with PZH.”
A business enquiry for Pilz? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeExtending the life of roads and civil engineering structures
- SubjectBridge construction
- CompanyPilz