‘First time right’ tunnel renovation

In the coming years, a number of tunnels in the Netherlands and Belgium will undergo major renovation. This is a complex operation, as many of these tunnels will only be partially closed to minimise disruption to traffic. The renovation must therefore run like a well-oiled machine. Infranea helps contractors with a risk-driven BIM approach focused on getting tunnel renovations right first time. This saves time, leads to better decisions and significantly reduces labour costs and the cost of rework.
Many of the existing tunnels in the Dutch and Belgian road networks no longer comply with current tunnel safety legislation. This is generally why ageing installations are replaced and fire safety measures are often upgraded. Infranea combines Systems Engineering and BIM for the digital preparation and delivery of tunnel renovation projects. “Our far-reaching digital approach often results in considerable savings,” says Johan Kuppens, founder of Infranea. “In this respect, we are at the forefront in the Benelux.”

Digital twin of A16 (TWIN 16) Visitors can experience the environment virtually in the driving simulator before construction.
Digital tunnel twin
According to Maarten van den Berg, BIM & SE Programme Manager at Infranea, this pioneering role is the result of an integrated approach and a strong focus on parametric modelling. “In 2019, for example, we meticulously prepared the Koningstunnel in The Hague on behalf of Heijmans and Siemens, primarily to keep potential risks during construction under tight control. In addition to the tunnel’s technical installations, those in the service building were also modernised and expanded to support the tunnel’s operation, monitoring and control. A 3D laser scan of the tunnel and the as-built data provided the starting point for a representative digital model of the existing situation. This data, combined with data on the surrounding area, forms the basis for the digital tunnel twin. The new tunnel systems were installed in this model. We were also able to assess how new systems could be installed in advance while the existing systems remained operational. This saves time.” Infranea used a similar approach for the renovation of the Velsertunnel, where the tunnel profile also had to be widened by 12 cm.

Digital twin of A16 (TWIN 16) Emergency scenarios can be tested virtually.
Lean design management
By making extensive use of computational design, BIM and a digital twin, Infranea, together with specialists from Heijmans and Siemens, managed to complete the Koningstunnel five weeks ahead of schedule. “That is a huge bonus in the middle of The Hague city centre,” Kuppens rightly points out.
“The aim was to use every technological tool available to renovate the tunnel right first time. And we succeeded. There were no technical costs of rework and only two outstanding items, neither of which could be attributed to the BIM model. The team was also deliberately kept as small as possible, reducing the risk of miscommunication.” Van den Berg adds: “Compared with previous projects, parametric modelling and computational design saved around three FTEs’ worth of engineering time on this project. There was no second or third tier of people who had to weigh in. We call it lean design management. The less-is-more principle: getting as much work done as possible with
as few people as possible. The engineers were also able to spend their time devising better solutions, rather than repeatedly processing frequent changes by hand.”
“Before a single grain of sand has been disturbed, the BIM model and digital tunnel twin allow us to simulate dynamic traffic behaviour, optimise CCTV cameras and check whether the software triggers the right processes in an emergency. We can also train tunnel operators and emergency services in advance,” Van den Berg continues. “All this technology is aimed at ‘buying time’ and reducing rework costs, so that tunnel renovation or new construction can be completed faster and more efficiently.”