Dynamic forces on bridges to be tested in practice from now on

Dynamic forces on bridges to be tested in practice from now on

TU Delft has gained an impressive movable structure. It looks as though it has been built from Meccano on a colossal scale and has a very important purpose: testing in practice the dynamic forces to which bridges are subjected. The driving force behind this high-profile test rig is Kodo Sektani, Engineer and Structural Asset Adviser at Antea Group.

We are sitting at the table with Kodo Sektani and Sonja Riesen, Project Manager for Movable Bridges at Antea Group. “The test rig is central to a study into extending the service life of movable bridges, initiated by Antea Group, Rijkswaterstaat and the Province of South Holland,” Riesen begins. “This rig makes it possible to test theoretical calculations in practice.”

Theory and practice do not match

The huge test rig is part of Sektani’s doctoral research. Asked why he started this research, he replies: “The Design Guidelines for Movable Bridges (VOBB) date from 1965 and were expanded in 2001 for new bridges, with calculation rules for dynamic forces. However, these rules are based on a series of simplified dynamic models dating from the 1980s. When existing movable bridges are reassessed, most of them theoretically fail to meet the requirements under the rules introduced in 2001. Yet observations from professional practice tell a different story. This made me realise that clear scientific research into this subject was needed.”

Since theory and practice were evidently far apart in many cases, Sektani saw a need for experimental research to develop a calculation model that could be verified and validated. “Verified calculation models can be applied to all bridges,” says Sektani. “The research focuses on the theoretical service life of bridge operating mechanisms. The models are verified and validated through precise measurements of the dynamic loads on components of existing bridge mechanisms. The ultimate aim is to develop a more realistic and reliable assessment model, bringing significant societal and financial benefits. In this way, we aim to prevent overdesign of bridge operating mechanisms and the premature, unnecessary replacement of components.”

In the test rig’s design, the first mass is represented by a flywheel with a variable shaft.

Focus on bascule and drawbridges

Sektani: “Among mechanically operated bridges, we distinguish four types: swing bridges, lift bridges, bascule bridges and drawbridges. Our focus is on the last two types, as they are the most common in the Netherlands. The bascule bridge has a Panama wheel with a crank and connecting rod, while the drawbridge uses a rack mechanism to move the bridge. Swing and lift bridges are not governing cases, as their mode of operation makes them less sensitive to wind loads.”

“The test rig has been designed to reproduce two different configurations, both the crank and connecting-rod mechanism and the rack mechanism,” Sektani explains.

Leaving nothing to chance

In the test rig’s design, the first mass is represented by a flywheel with a variable shaft. “This represents the flexibility of the drive train,” Sektani explains. A linear spring represents the flexibility of the bridge deck. The second mass is represented by another flywheel: “This compensates for the bridge’s mass inertia.”

A buffer unit is used. Sektani: “In practice, movable bridges use what is known as a spring buffer, consisting of a stack of preloaded disc springs. Its purpose is to press the closed bridge deck down onto its supports, preventing it from rattling when traffic passes over it. However, this buffer affects the forces involved when the bridge deck opens and closes, by adding friction, play and spring action to the dynamic system. For the test rig, we have designed a special buffer made up of three separate modules, which allow us to measure the effect of these variables on dynamic loads separately.” Current theory does not take all these variables into account. Practical testing is the only way to find out which variables can be disregarded. “Only once we know which variables do not need to be included can we develop a simplified reduction model of reality,” says Sektani.

No scale effects

“We chose a test rig of this size because of the upper and lower limits. If it were too small, scale effects would occur; if it were too large, it would be too costly,” says Riesen. Sektani adds: “At its current size, we are indeed free from scale effects and can use standard components for the fabricated parts. Most of these have been donated by our sponsors.” Speaking of sponsors, Sektani is amazed by their willingness to invest and expresses his gratitude to all the parties that have contributed. Riesen sees this as a result of the tremendous drive Sektani brings to the project. “Kodo is at the centre of it all, like a spider in its web, and everyone is convinced this plan will succeed. Building bridges over water is easier than building bridges between people, but everyone is on board. It is all for the benefit of society in the Netherlands.”

Sektani concludes: “Putting the test rig into operation was a very special moment. I didn’t want to leave the lab either. It had been such a struggle to get everything in place. The opening of the test rig was therefore one of the happiest moments of my life.”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectBridge construction
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.