Bridge construction

A colossal project involving 53 bridges, 74 PLCs and 3 control centres

A colossal project involving 53 bridges, 74 PLCs and 3 control centres

‘The Christmas Tree’ was the affectionate nickname for the test rig. Never before had so many PLCs been used in a single project anywhere in the world. Pilz did it in a project commissioned by the Province of South Holland to modernise the automation of 53 bridges. Pilz’s test rig consisted of panels packed with electronics, set up side by side. Project engineer Ricardo Duijser believes it was the management team who, on their arrival just before Christmas, fondly dubbed the rig with all its flashing lights ‘The Christmas Tree’. “That became the working title for our project from then on,” says Duijser.

The test rig was a dry simulation of the project. Duijser: “The end result was a stable, fully operational system that we were confident enough to roll out. We carried out the first tests a year ago on the Merwedekanaal. There, we connected 2 control centres to 8 bridges. It has now been running fault-free for more than a year. We began rolling out the rest, covering a total of 53 bridges, in August 2018.”

Each bridge can be dynamically connected to any control centre
“Previously, a bridge could be connected to a maximum of 2 control centres. That has now changed: each bridge can be dynamically connected to any control centre. This greatly improves safety,” Duijser explains. “The old setup used the PSS 3000 (Pilz Safety System), which has been phased out. The new PSS 4000 system used in this rollout offers many more possibilities. Using the Ethernet protocol means there are no longer any bus limitations.”

De Kerstboom

Given the number of PLCs used, this project is unprecedented anywhere in the world.

To ensure availability, everything is interconnected. This makes it easy to switch over to another control centre in the event of a fault. “The control centre manages operations, with between 8 and 16 operator stations at each centre,” Duijser explains. “Given the number of PLCs used, this project is unprecedented anywhere in the world. That places considerable demands on our organisation and our people. To give you an idea: a total of 23,694 lines of code were needed to run the system. The project contains 554,989 local variables, 8,698 of which are, so to speak, sent out into the ether to communicate with the outside world. No fewer than 319 Modbus connections are active to communicate with the operator stations. To get all the data to the right place, there are 540 SafetyNetp connections, our Ethernet-based safety protocol.”

Met de kooiladder wordt op een duurzame manier de veiligheid op projecten verhoogd.

Using the Ethernet protocol means there are no longer any bus limitations.


Everyone pulls together
The rollout across the 53 bridges began in August 2018. The bridges were modified, and the system migration took place in November. Duijser explains: “The three control centres had to be switched over one at a time. Each weekend, we took responsibility for one control centre and its associated bridges. Looking back, we can be satisfied with a real team effort. This colossal undertaking shows how Pilz works: everyone pulls together. We dare to take on the challenge of going one step further because this kind of work brings us all together at Pilz. I’m proud of that.” 

A business enquiry for Pilz? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectBridge construction
  • CompanyPilz
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.