The Key Register of the Subsurface will be a “game changer” for geotechnical engineering

Digital data flows: A vision for data in geotechnical engineering, by Kees-Jan van der Made, chair of the Vereniging Ondernemers Technisch Bodemonderzoek (VOTB).
Subsurface data will be decisive for the construction sector’s survival. The nitrogen and PFAS crises are serious warnings. Once the coronavirus crisis is over, climate targets will come back into focus. And rightly so. The construction sector will be expected to reduce emissions: less nitrogen, less PFAS,
less CO2.
So we would have to build less, costing jobs and putting ambitions, such as those for housebuilding, at risk. Or do we seize the opportunities that digital subsurface data offer us now? More digital data and knowledge of the subsurface will enable better risk analyses, allowing us to keep building on the same scale as today, but with a smaller ecological footprint. Geotechnical investigation companies, represented by the industry association VOTB, and geotechnical consultants can play an important role by applying their expertise to the correct interpretation of measurements, the development of models and the carrying out of calculations.

Since 2018, digital subsurface data have been actively collected under the Key Register of the Subsurface Act. The clock is ticking: all that data must be converted into 3D subsurface models for projects, making uncertainties visible in a 3D spatial computer model so that targeted further ground investigations can reduce them and lower the risk of failure. Clients have an important role to play in this process by specifying a maximum level of uncertainty for ground models in their contracts before design work begins and a final design is approved.
“There is no benchmark at present. You can design a structure using just 2 cone penetration tests, but that leaves you with an unknown risk and makes the project unnecessarily expensive because you build in extra safety margins or take costly mitigating measures. As taxpayers in the BV Nederland, we always end up paying the price. None of the parties involved in a project represents our interests, even though we fund everything, including when things go wrong.”
So now is the time to seize the opportunity. Everyone stands to benefit. Research institutes, public-sector bodies such as water authorities, and commercial organisations must now play their part, because the BRO will be complete in 2022. To prevent unfair competition funded by taxpayers’ money and to encourage development, it is important to align all parties’ roles within a long-term vision.
Changes on the way
The geotechnical sector is undergoing significant change. The BRO is bringing changes to our market, including:
- Data providers are responsible for publicly available data in the BRO for 10 years, and the data are more readily available than in the past;
- Data in the BRO are “raw”, unlike the syntheses that customers are used to;
- Field descriptions and sample containers are kept separate and are not combined;
- The data are in a different format from the one we are used to. This has implications for presentation and calculation software;
- Additional data are made available digitally through the BRO, with an obligation to use them;
- Software for automated calculations using the BRO will become available. The new drilling standard 14688 is also bringing changes to our market:
- Certain soil-type designations no longer exist, marking a break with the past;
- Fine-grained soils are classified by their behaviour, rather than by the percentages of their fractions;
- The proportions of the fractions used to classify soil types have changed (GRAVEL-SAND);
- The designations for secondary fractions have been restricted;
- New fields are mandatory (layer boundaries, lime, moisture, etc.), and there are other requirements for describing layering, among other things;
- Different classification descriptions are used;
- Part 2 specifies index tests for classifying soil
- A more detailed description, particularly in relation to index tests, is needed to ensure tenders can be specified consistently.
- The BRO will make it possible to generate STOWA-style tables automatically from this raw data, in line with current understanding, and keep them up to date.
- The Eurocode currently being developed at European level is also bringing changes to our market:
- A desk study in advance will become more important, particularly in the Netherlands, where the BRO is among the relevant resources;
- Ground investigation reports will be expected to include a ground model and a synthesis of the data.
These changes are both a threat and an opportunity. Time is running out to respond to them. The following paragraphs offer some initial ideas.

A vision for ground investigation
The ground is one of the major risks for infrastructure projects, yet ground investigation typically accounts for less than 1% of construction costs. The Geo-Impuls programme (2009-2014) successfully helped to embed practices such as risk-based ground investigation and the reduction of geotechnical failures in the civil engineering sector.
What next? As more and more data become available in the BRO, standards change, 3D design, BIM and automated calculations become more widespread, and knowledge increases, there is a growing need to take a different approach to future ground investigations, building on CUR247.
A nationwide subsurface model based on stratigraphic scenarios, with associated likelihoods and default parameter values, is already available for dikes and is expected to be expanded to cover the civil engineering sector. To refine it for specific project sites, it makes sense, following a desk study, to develop a targeted collection of test results for geotechnical units, alongside gaining a better understanding of their spatial distribution. A thorough investigation at selected pilot sites, including high-quality cone penetration tests, boreholes with index tests, sufficient laboratory testing of strength parameters, and monitoring of pore water pressures, can provide an early insight into optimal geotechnical units, possible correlations and links to existing available data. This is already being done for dike investigations. It is not yet being done for other civil engineering projects.
The future
The clock is ticking: all that digital data must be converted into 3D subsurface models for projects, making uncertainties visible in a 3D spatial computer model so that targeted further ground investigations can reduce them. Clients can then specify a maximum level of uncertainty within a ground model before design work begins. By reducing unnecessary safety margins in designs and uncertainty about the subsurface, we can produce cheaper designs and deliver more construction projects.
To design geotechnical solutions responsibly in the future using new digital techniques such as artificial intelligence, automated calculations, BIM and 3D models, and to realise the benefits for the BV Nederland, databases such as the BRO and high-quality investigations will be essential. The vision for ground investigation on publicly funded projects, where the data are stored in the BRO and made available to everyone, should reflect this. The current approach to ground investigation can sometimes seem “penny wise, pound foolish” for the taxpayer.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectBouwMat