‘Recycled’ Gevlebrug reaches its final destination today

Today marks the start of the final phase of a literally fine example of reuse. The Gevlebrug, built in 1930, was moved yesterday from its restoration site at Damen Shiprepair Amsterdam to the opposite bank of the IJ, ready to be installed at its permanent location today.
The bascule bridge served until 2002 to the east of Central Station, but could not carry the trams to IJburg and therefore had to be replaced. It was then used for a time at Noorderhoofd, an area in the Port of Amsterdam. Following a major renovation, the distinctive bridge is now set for a new role as one of the access roads to Houthavens, a new district in Amsterdam.
Space
The restoration was carried out by Niron Staal Amsterdam BV and Fa. Evenboer on behalf of Gebr. Beentjes Grond-, Weg- en Waterbouw, in one of the four dry docks at Damen Shiprepair Amsterdam. “It’s great that we still have space in Amsterdam, relatively close to the city centre, to carry out major projects like this,” says Tjeerd Schulting, director of Niron Staal and Damen Shiprepair Amsterdam.

Dry dock
While Fa. Evenboer restored the existing bridge in the dry dock, Niron Staal fabricated three new bridge decks in its workshop: one road deck, 6 metres wide and 28 metres long, and two pedestrian decks, each over 3 metres wide and 28 metres long. Once the work was complete, the old bridge, named after the Swedish Baltic Sea port of Gävle, once an important hub for the timber trade with Amsterdam, was transported to the workshop and the decks were mounted on the existing bridge.
Modular trailers
Last Thursday, the fully assembled bridge was transported from Niron Staal’s workshop to the load-out quay at Damen Shiprepair Amsterdam using a specialist transport system with self-propelled modular trailers. The bridge was loaded onto a pontoon there and taken across the IJ. Yesterday, it was brought ashore at Houthavens, after which the same modular trailers will be used to move it into position today.
Question about this story? Ask your question
Who worked on Gevlebrug
- restorationFa. EvenboerIn this story
- restoration siteDamen Shiprepair AmsterdamIn this story
- restorationNiron Staal Amsterdam BVMentioned in ‘Recycled’ Gevlebrug reaches its final destination today
- natural stoneMeesters InMentioned in Rebuilding iconic Gevlebrug in Amsterdam calls for multidisciplinary collaboration
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGevlebrug
- ThemeMaterials and techniques for infrastructure
- SubjectBouwMat
- CompanyFa. Evenboer
- CompanyDamen Shiprepair Amsterdam