Innovative. Compact. Sustainable

A new wastewater treatment plant is being built in Weesp. The ICEAS treatment process meets the highest standards, is compact and requires relatively little energy. This innovative treatment plant will ensure Weesp is ready for the future once again.
Waterschap Amstel, Gooi en Vecht is having the ICEAS treatment plant built on the site of the existing wastewater treatment plant (RWZI) in Weesp. This RWZI is outdated and will no longer be able to meet the discharge requirements for water outflow in 2020. Waterschap Amstel, Gooi en Vecht tendered the water treatment plant under the Uniform Administrative Conditions for Integrated Contracts (UAV-GC), for design & construct with one year of maintenance. It set out the requirements the plant had to meet, leaving the contractors to develop the best solution.

Treatment tank for the ICEAS treatment process. (Image: Fabion)
Project start-up
“Waterschap Amstel, Gooi en Vecht ultimately chose ICEAS technology,” says Andre Edelenbos, CSO of Moekotte Groep. “As many parties are involved in delivering a plant like this, the construction consortium first organised a project start-up after the contract was awarded. The partners met and got to know one another in an informal setting. Weekly meetings of the core team followed. The same parties work together and share their expertise to deliver the best plant. Moekotte Groep is responsible for the electrical installations.”
ICEAS
The entire treatment process in the ICEAS plant, including reaction, settling, decanting and stabilisation, takes place in a single tank. This differs from conventional wastewater treatment plants, where the process is divided between several tanks. The new process saves space and construction costs, creating scope for future expansion, for example. “The population of Weesp has grown considerably in recent years and is expected to continue to rise,” says Wolter Wolthers, project manager at Moekotte Groep. “With the treatment plant’s increased capacity and scope for expansion, Weesp will be ready for the future once again.”

Visualisation of the treatment plant. (Image: 3Dimensions vof)
Ready to go
The engineering firm produced the initial design, which was developed into a final design and then into a construction design. Wolthers: “The civil engineering contractor could then start the building work, while the mechanical engineering contractor installed the equipment. Moekotte Groep comes into the picture mainly when the electrical installations need to be cabled and connected.”
“Every project has its ups and downs, and this one was no exception,” Edelenbos admits. “We had set ourselves a tight schedule. This was only achievable with perfect engineering at the preliminary stage. In practice, you encounter changes that slow the process down. The positive side is that everyone kept talking to one another and we worked together to find solutions. All the parties always kept the same goal in
sight.”
Question about this story? Ask your question
Who worked on ICEAS-zuivering Weesp
- electrical installationsMoekotte GroepIn this story