Building foundations for roads, cycle paths, reinforced verges, parking areas and hard standings generally requires a constant supply of primary construction materials and a great deal of transport. Terrastab takes a different approach, using locally sourced material to quickly create a stable, high-quality structure. No material needs to be removed or new foundation material brought in.
Excavating, removing, bringing in new material and processing it often takes a great deal of time on civil engineering projects. Terrastab specialises in soil stabilisation, reusing 100% of the existing material on a project. “This allows us to upgrade the soil or even give it a new function, without having to bring material in or take it away,” says Erwin Bonestroo of Terrastab. “That is a major advantage, particularly in light of the current PFAS issue.”

Romans
According to Erwin, the soil stabilisation technique used by Terrastab is as old as the road to Rome. “The Romans already used this tried-and-tested technique, which we have naturally developed further and extended. For each project, we assess the composition of the locally sourced material and select the right binders and additives based on the intended future loads. Soil stabilisation for a cycle path, for example, requires a different mix from that for a crane hard standing at a wind farm construction site. The additives and binders, whose composition is determined in our own laboratory, make up only a fraction of the total and are almost insignificant in comparison. This also enables us to achieve a huge reduction in CO2 emissions compared with the traditional method.”

Terrastab specialises in soil stabilisation, reusing 100% of the existing material on a project, in this case a road surface in Castricum without a wearing course.
High compressive strengths
Technical expertise and a healthy dose of creativity set Terrastab apart in the world of soil stabilisation. Erwin says: “In recent years, we have worked on leading projects in the Netherlands and abroad. The technique has more than proved its worth, with the ability to achieve high compressive strengths, work on dike slopes and build foundations for airports. Structural engineers and civil engineers are also enthusiastic about our method. With our own R&D department and laboratory, we continue to develop optimal structures and expand the range of applications. Alongside our proven reinforced verge solution, which has a service life of around ten years, we are now developing verge concrete made from locally sourced material, again without bringing in primary construction materials. This allows us to lay between 700 and 1,000 metres of verge concrete per day, fully finished and ready for use. That is more than three times as much as with the traditional method.”
Een zakelijke vraag aan Terrastab Nederland B.V.? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectBouwMat
- CompanyTerrastab Nederland B.V.