From dredged sediment to dike clay: “Building with Nature”

At a site covering around 15 hectares in Delfzijl, clay made from dredged sediment from the Eems-Dollard is maturing. The pilot project, known as the “Kleirijperij”, was conceived and carried out by a consortium comprising Ecoshape (Van Oord, Boskalis, Arcadis, RHDHV, Witteveen+Bos, Wageningen Marine Research and Deltares), Groningen Seaports, Rijkswaterstaat, Het Groninger Landschap, Provincie Groningen and Waterschap Hunze en Aa’s.
The aim of this pilot? To produce usable clay that can be used to strengthen a disapproved sea dike along a 12.5 km stretch. We discuss this unique project with Marcel van den Heuvel, Technical Manager for Kleirijperij and Engineering Specialist at Van Oord, and Erik van Eekelen, Programme Manager at EcoShape and Lead Engineer Environmental at Van Oord.

Erik van Eekelen, Programme Manager at EcoShape and Lead Engineer Environmental at Van Oord, on the left, and Marcel van den Heuvel, Technical Manager for Kleirijperij and Engineering Specialist at Van Oord, on the right.
A major step forward for the water engineering sector
We ask why Van Oord is involved with Ecoshape. Van Eekelen explains: “Van Oord places great importance on Building with Nature. Innovative developments that contribute to greater sustainability in the water engineering sector matter to everyone. We are happy to share our knowledge so that everyone can benefit from it. This makes water engineering projects better and, as a result, more achievable. Through the Building with Nature principle, we want to think proactively about the use of natural resources in ways that benefit the ecosystem. This is of great importance to society, not only for Van Oord as a contractor, but for the entire Dutch water engineering sector.”
100% green building material
The Kleirijperij pilot in Delfzijl uses dredged sediment from the Eems-Dollard. Through a natural process, the sediment is expected to consolidate and eventually produce firm clay. “The great thing is that what is in excess in one place, dredged sediment, can ultimately be used to address a shortage elsewhere, namely a shortage of clay. The embattled dike can soon be strengthened with matured clay in a 100% green way,” says Van den Heuvel. “Because clay does not need to be transported from distant areas, this approach is even more sustainable. Better still, using clay as a natural building material means the dike retains its green character. Where asphalt would otherwise have been used, we will have a 100% green building material for reinforcement.”

July 2019: the maturing sediment is already developing a true clay structure. (Image: Deltares)
Pilot follows on from an initial trial
“The idea first emerged in 2014, when EcoShape launched a programme with the Wadden Sea ports, all of which have problems with sediment. A relatively large amount of maintenance dredging takes place, and there is limited scope for intervention because the Wadden Sea is a UNESCO World Heritage Site. Together, we defined projects, including the Delfzijl salt marsh trial and the sediment engine in Harlingen. Sediment management is a major issue. EcoShape partners were already working on the Eems-Dollard problem when the water boards approached us about dike reinforcement and began looking for an alternative to conventional asphalt. Green dikes have landscape value, which is why there is such a high demand for clay,” Van Eekelen continues. “In 2015, we got together to discuss our ideas, which we wanted to test at full scale. In July 2017, 6 parties signed an agreement to carry out the trial. We have now prepared a few hectares of land, and the Kleirijperij is a reality. The first sediment arrived at the depot on 5 April 2018.”
The 15 trial cells, or depots, each measure just under 100 x 100 metres and have an average depth of 1.5 metres. “Everyone was surprised by how quickly a crust formed on the depots, which had been filled with liquid sediment with a consistency like chocolate milk. The crust quickly reached a thickness of 30 to 40 cm; the clay dries out through shrinkage and consolidation. This allows more oxygen to enter,” explains Van den Heuvel. “It is partly a physical process and partly a chemical one. Water, salt and organic matter (algae and so on) have to be removed to produce dike clay that meets the applicable requirements for density, salt content and organic matter.” Van Eekelen adds: “The requirements for dike clay have been translated directly into the pilot.”
A second site is now up and running
A second site has since been added, bringing the total number of trial cells to 25. “No two cells are the same. We vary the layer thickness; some have a draining sand layer, while others have more active treatment layers. We also allow vegetation to grow in some cells, and one cell is half-filled with fresh water to influence salt removal. The pilot will be a success if we can develop a sound business case,” says Van den Heuvel.
For Van Oord, it is important to map out the processes that can be used to convert other types of sediment. “If the technique can be tailored to sediment in particular areas anywhere in the world, then clay can be produced close to the source. In some parts of the world, this could be an excellent solution. That is why we need to find out how to identify the type of sediment, what kind of clay is needed and which process is appropriate,” explains Van Eekelen. “For Van Oord, the key is making this approach more widely applicable. This is a technical matter, but it is also very much about environmental management, with nature becoming an essential component of the overall approach.”
Have a business enquiry for Van den Heuvel? Get in touch
Who worked on Kleirijperij
- consortiumWageningen Marine ResearchMentioned in From dredged sediment to dike clay: “Building with Nature”
- consortiumGroningen SeaportsIn this story
- consortiumRijkswaterstaatIn this story
- consortiumHet Groninger LandschapIn this story
- consortiumProvince of GroningenIn this story
- consortiumWaterschap Hunze en Aa'sIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectClay ripening facility
- ThemeFlood protection and climate-resilient water management
- SubjectBouwMat
- CompanyVan den Heuvel
- CompanyGroningen Seaports
- CompanyRijkswaterstaat
- CompanyHet Groninger Landschap
- CompanyProvince of Groningen