Construction of outer lock head cofferdam for Nieuwe Sluis in Terneuzen well under way

Work is proceeding around the clock in Terneuzen to build the cofferdam for the outer lock head.
The lock heads are being built inside a dry cofferdam, where work will take place on both sides of the lock chamber to construct the gate recesses, bridge chamber and water-level equalisation system. The outer lock head, on the Western Scheldt side, is slightly ahead of the inner lock head on the Ghent-Terneuzen Canal side.
The outer lock head cofferdam was first excavated dry to -11 metres NAP, and will ultimately be -22 metres NAP deep. To reduce the upward pressure on the base, after dry excavation the outer lock head cofferdam was filled with approximately 15,000 m3 of canal water. Two excavators then worked from a 55 x 22-metre pontoon in the cofferdam to excavate underwater to -22 metres NAP. This work is currently in full swing at the inner lock head.

12,000 cubic metres of underwater concrete
Most of the excavated material from the underwater excavation was pumped through the existing pipeline route. Material that could not be reused was sent for disposal aboard vessels in Buitenhaven-West. Reusable material was sent via a branch of the pipeline route to one of the soil storage sites elsewhere on the construction site. Once the dry and underwater excavation was complete, it was time to pour underwater concrete at the base of the outer lock head cofferdam. First, a layer of gravel was laid as a base for 1 metre of underwater concrete. The concrete was poured on 4, 5 and 6 August 2020 in a continuous operation. Divers worked around the clock, 24 hours a day for 3 days, to pour a total of 12,000 cubic metres of underwater concrete. The operation had to proceed without interruption to ensure the quality of the concrete floor.
Production at the project's own concrete batching plants
The project's own concrete batching plants are located at the Zeevaartweg construction site, where the underwater concrete was produced. A total of 60 tonnes of cement was used, delivered from Belgium by 2 bulk trucks per hour. As the operation could not be interrupted, a ship carrying cement was kept on standby as a back-up in case anything went wrong with road deliveries. Sand and gravel for production were delivered by ship during the day.
This approach was in line with the plan to minimise disruption as much as possible. Having the concrete batching plants on site meant that concrete mixer trucks did not have to use public roads. In addition, producing the concrete on site made it possible to ensure consistent quality of the underwater concrete.

Pumping out the cofferdam
The underwater concrete has now hardened and the cofferdam is being pumped dry. The thick concrete floor, combined with dewatering, keeps the pressure under control and prevents the floor from bursting upwards. Dewatering is being carried out carefully and under close control. Groundwater is extracted from beneath the cofferdam and then discharged into different soil layers nearby, so the impact on the surrounding area is negligible. Water levels around the cofferdam are monitored, as is the stability of the façades of several houses in the centre of Terneuzen. Survey bolts have been installed in the façades for this purpose. The dry cofferdam is approximately 25 metres deep.