Construction of Nieuwe Sluis’s outer head in Terneuzen in full swing

Construction of Nieuwe Sluis’s outer head in Terneuzen in full swing

Work is in full swing in Terneuzen to construct the cofferdam for the outer head.

The lock heads are being built in a dry cofferdam, where work on the gate recesses, bridge basement and levelling system will take place on both sides of the lock chamber. Work on the outer head, the lock head on the Westerschelde side, is slightly ahead of work on the inner head on the Kanaal Gent-Terneuzen side.

The cofferdam for the outer head was first excavated dry to -11 metres NAP. It will eventually need to be 22 metres deep, to -22 metres NAP. To reduce the upward pressure on the bottom, the outer-head cofferdam was filled with around 15,000 m3 of canal water after the dry excavation. Two excavators on a 55 x 22-metre pontoon in the cofferdam then carried out wet excavation down to -22 metres NAP. This work is currently in full swing at the inner head.

12,000 cubic metres of underwater concrete

Most of the excavated material from the wet excavation was pumped through the existing pipeline route. Non-reusable soil was transported away by ship from Buitenhaven-West. Reusable soil was sent via a branch of the pipeline route to one of the soil storage areas elsewhere on the construction site. Once the dry and wet excavation work was complete, it was time to pour underwater concrete on the bottom of the outer-head cofferdam. First, a gravel layer was laid as a base for one metre of underwater concrete. The concrete was poured on 4, 5 and 6 August 2020 in a continuous operation. For a full 24 hours a day over three days, divers helped pour a total of 12,000 cubic metres of underwater concrete. The operation had to be carried out without interruption to ensure the quality of the concrete floor.

Production at the on-site concrete plants

The on-site concrete plants are located at the Zeevaartweg construction site, where the underwater concrete was produced. A total of 60 tonnes of cement was used, delivered from Belgium in two bulk tankers per hour. As the operation could not be interrupted, a ship carrying cement was kept on standby as a back-up in case anything went wrong with road deliveries. Sand and gravel for production were delivered by ship during the day.

This approach was in keeping with the plan to minimise disruption as far as possible. Having the concrete plants on site meant that concrete mixers did not need to use public roads. In addition, in-house production made it possible to ensure consistent quality of the underwater concrete.

Pumping out the cofferdam

The underwater concrete has now hardened and the cofferdam is being pumped dry. The thick concrete floor, combined with dewatering, keeps the pressure down and prevents the floor from bursting upwards. Dewatering is carried out carefully and under controlled conditions. Groundwater is extracted from beneath the cofferdam and then reintroduced into various soil layers nearby, keeping the impact on the surrounding area negligible. Water levels around the cofferdam are monitored, as is the stability of the façades of several houses in the centre of Terneuzen. Survey markers have been installed on the façades for this purpose. The dry cofferdam is around 25 metres deep.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectBouwMat
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.