De Stouwe pumping station
Text Roel van Gils Beeld Van Heteren Weg- en Waterbouw

A compact masterpiece
Waterschap Drents Overijsselse Delta (WDODelta) faces a huge challenge. It manages 370 pumping stations and 1,980 weirs, which are renovated or replaced on average once every 25 years. To make the process more efficient and future-proof, the water authority signed a framework agreement with three contractors in 2023. Van Heteren Weg- en Waterbouw is one of them, and is currently working on the renovation of De Stouwe pumping station: a compact masterpiece where almost everything comes together.
Pumping stations and weirs have a service life of around 30 years. “After that, they need to be replaced for technical and functional reasons,” says Jannick Knol, design lead at Waterschap Drents Overijsselse Delta. “The framework agreement allows us to renovate or replace more assets in a shorter time. Each contractor carries out an average of five projects a year, which means we can make significant progress.” Ewout Aman, project manager at Van Heteren, adds: “A design-and-build team makes collaboration much more intensive. You build up knowledge, learn how each other works and can therefore respond more quickly. For us as a contractor, it also means we have projects continuously in the design, construction and aftercare stages.”

Respect for the past
De Stouwe has a long history. A sluice was once located here to protect the hinterland from flooding when the Vecht was in spate. In the 1990s, a pumping station was built on the same site, integrated into the old sluice. Now, more than 30 years later, the pumping station itself is due for renovation. “The old sluice no longer serves its original purpose, but we wanted to restore it,” Knol explains. “The new installation was designed independently of the sluice, while respecting the historic context. The design does justice to the site’s history while meeting current water safety requirements.” The pumping station is also located in the middle of a primary flood defence. “Part of the defence turned out to be too low,” says Aman. “We took the opportunity to raise it as part of the Flood Protection Programme, bringing 50 metres of flood defence up to the required height so the area will remain well protected in the future.”

A complex water management challenge
De Stouwe is on a small plot measuring just 20 by 10 metres. Yet the pumping station had to be able both to supply and discharge water. Knol explains: “That makes this site unique. Usually, a station does one or the other. Here, we need to do both. In dry periods, we pump water in using two pumps; in wet periods, we discharge it via the weir. But when the Vecht is high, water can no longer flow away under gravity. During high water, a ‘high-water pump’ then switches on, capable of pumping as much as 96 cubic metres per minute.” Aman adds: “And all of that on just a few square metres, while preserving the old sluice and working right in the middle of the flood defence. It is a huge technical and spatial puzzle.” In addition to pumps and weirs, the design also includes a fish pass. It is the first fish pass in WDODelta’s operational area. “It allows fish to migrate both upstream and downstream, as required under the European Water Framework Directive.”

Quality of the built environment
The design of the superstructure, the building that houses the pump motors, has been carefully considered in terms of appearance and sustainability. “Together with the architect, we chose circular cladding,” says Knol. “Azobé planks salvaged from elsewhere are being given a second life here. The design was also inspired by the old sluice. This is how we connect the past with the future.”
The surrounding area will benefit too. Aman says: “We are reinstating a small bridge that was blown up during the Second World War. And we are making the old road from Ommen to Dalfsen visible in the paving. This brings the history to life.”

Involvement
The collaboration with Deltion College in Zwolle is also noteworthy. Students are making replicas of the old sluice gates based on historical photographs. The gates will be placed in the water as visual features, just below the waterline. “It is a wonderful way to involve young people in our work,” says Aman. “They learn not only about the technology, but also about the value of cultural heritage.” Involving local residents was just as important. Knol says: “We are literally working in the neighbours’ garden. We could not have delivered this project without their cooperation. We have had good discussions with them, which has helped enormously.”

On schedule
Van Heteren began construction of De Stouwe pumping station in April 2025, just after the high-water season. “We have enclosed the pumping station with sheet piles. A temporary pumping installation is managing water levels during construction, and it can also pump in both directions if necessary,” Aman assures us. In his view, work is still progressing exactly to schedule. The project is due to be completed in December as planned.” At the same time, the design-and-build team is working on several other projects, from small weirs and inlets to new pumping stations already in preparation for 2026. This demonstrates the strength of the framework agreement: there is always a continuous pipeline of projects at different stages. This enables WDODelta and its partners to maintain a steady flow of work and a future-proof asset base. “Pumping stations and weirs are crucial links in water distribution. They supply or discharge water, keeping water levels in an area under control and maintaining the right balance between too much and too little water.”
De Stouwe pumping station is much more than a technical renovation. It is a project that brings together history, innovation, sustainability and collaboration. An installation is being built on a small plot that is ready for the future while also doing justice to the past. With modern technology, sustainable materials and committed partners, a compact masterpiece is taking shape here.
Question about this story? Ask your question
Who worked on it
De Stouwe
- contractorVan Heteren Weg- en Waterbouw
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDe Stouwe
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyVan Heteren Weg- en Waterbouw