Schijnkoker works in Merksem fully completed

Preparatory work for the Oosterweel works has been under way in Merksem for several years. This week, we completed our largest preparatory project here: relocating the Schijnkoker. This concrete culvert stood in the way of building the Bypass and constructing the sunken ring road. To continue protecting the Merksem neighbourhood of Rietschoorvelden from flooding in the future, we first built a new culvert before demolishing the old one. The new culvert went into service last summer. This week, demolition of the old culvert was also completed. The area between the Rietschoorvelden neighbourhood and the Antwerp Ring is now fully ready for construction of the Bypass.
As part of the Oosterweel works, we are not only lowering the motorway below ground, but also building large covers over the new motorway. The old Schijnkoker stood in the way. To prevent the neighbourhood from being exposed to flooding again, we first built a new Schijnkoker closer to the neighbourhood over the past few years. We also diverted water and gas pipes and sewers. In summer 2024, we brought the final section of the new Schijnkoker into service. We then began demolishing the old culvert.


From river to floodwater buffer
The Schijnkoker runs alongside the E19 in Merksem. It is a remnant of the River Schijn, which was once enclosed in a culvert. After severe flooding in the 1990s, the river was cut off at the Albert Canal. The culverts were left underground and have served as a buffer ever since. When the regular sewers could not cope with the rainwater, it overflowed into the Schijnkoker, protecting the neighbourhood from flooding.
Excess water now flows away through the new, twin Schijnkoker. Each culvert measures an impressive four metres by two metres. The rainwater is then pumped into the canal via a pumping station on the Albert Canal.
Hello Bypass, goodbye viaduct
With all the obstacles removed from underground, the way is clear for construction of the Bypass. This temporary motorway, running alongside the current R1, will keep traffic on the motorway during the Oosterweel works and out of the residential areas of Deurne and Merksem.
From late 2025, traffic heading towards the Netherlands will use the Bypass from the Sportpaleis, allowing us to demolish the first section of the old viaduct. Another step towards the ultimate goal: a more mobile and liveable city, and the removal of the concrete barrier that the viaduct represents today.