A2/N2 underpass: final piece in Eindhoven Northwest area development
Text Roel van GilsImage Paul Poels and Roel van Gils

For 5.5 years, major work has been under way in Eindhoven Northwest to improve traffic flow and access to, among other places, Brainport Industries Campus (BIC), GDC Acht business park and Eindhoven Airport. By car, bicycle and public transport. The Municipality of Eindhoven and Strukton, together with their partners, are currently working on the third and final phase, whose centrepiece is the underpass taking the new road beneath the A2/N2. Last summer, the ‘tunnel sections’ were successfully moved into position. We travelled the first few metres through the new underpass with alderman Stijn Steenbakkers (Eindhoven Northwest and Brainport area development), project manager Sjaak Gerritsen (Strukton) and project leader Hendrik-Jan Vennix (Municipality of Eindhoven).

From chicken to chip
“The Municipality of Eindhoven has designated Eindhoven Northwest as a strategic development location, just like, for example, the Spoorzone area, which includes Internationale KnoopXL,” Steenbakkers begins. “As alderman, I am responsible for developing these areas. Eindhoven Northwest is special in that several strategic functions come together here. The airport, GDC Acht and the development of Brainport Industries Campus (BIC) 1, where various high-tech manufacturing companies work alongside educational institutions under one roof on the economy of the future. In November 2022, Eindhoven city council approved the first steps towards expanding BIC 2, which will add a further 225,000 m2, where Brainport businesses and educational institutions can work on innovative, high-tech solutions to societal challenges, for example in healthcare, mobility and energy. At the same time, there is a strong focus on green space and nature development. Stadsbos runs through Eindhoven Northwest, and in the future we will open the 142-hectare De Wielewaal estate to the public. This is truly a special area, which could also be described as the region of ‘chicken to chip’.”

Investing in accessibility
According to Vennix, the development of Eindhoven Northwest is one of the largest infrastructure expansions since the early 1960s. Steenbakkers adds: “It is important that we invest in making our city accessible. This project is crucial to providing access to the area and reducing congestion on the A2/N2 and A58, as well as easing pressure on Anthony Fokkerweg. Alongside car and freight traffic, the area development also focuses on promoting sustainable transport, such as cycling and public transport. Accessibility is considered from a multimodal perspective. The cycle bridge over the A2/N2, a cycle tunnel beneath Anthony Fokkerweg built in an earlier phase, and HOV3, Eindhoven’s third high-quality public transport line, are good examples. The Wegenstructuur Eindhoven Noordwest project is funded by the Ministry of Infrastructure and Water Management, the Province of North Brabant, the Municipality of Eindhoven and the Municipality of Oirschot.”

Alternative to reference design
Strukton is responsible for delivering the third and final phase, as part of a construction team with the Municipality of Eindhoven. “The project involves building an underpass for a new road beneath the A2/N2, up to the roundabout at GDC Acht business park,” says Gerritsen. “The tender did include a reference design for the underpass, but it also allowed us to propose an alternative. We reworked the original wall-and-roof construction method into one involving the installation of precast elements. We won the contract with this incentive, which focused on minimising disruption. By also phasing the work intelligently, we were able to keep the A2 open to traffic in both directions throughout.” To achieve this, Strukton set up a construction site on both the west and east sides of the A2/N2, where it built two tunnel sections in advance. “The four sections were between 21 and nearly 30 metres long, all 12 metres wide and weighed around 1,300 to 1,900 tonnes,” says Vennix. “The tunnel sections were moved into position in the middle of the 2022 summer holidays.”

Technical highlight
Moving the four tunnel sections into position was undoubtedly the technical highlight of the project. “First, capacity on the A2/N2 was halved under a temporary traffic management system. During the 3.5 weeks of work, half of the 15 lanes in total remained open in both directions,” Gerritsen explains.
“We then started on the west side by breaking up the motorway and excavating the route to make room for the two tunnel sections. The approach has a sand-on-sand bed, levelled and graded to allow both sections to be moved down in turn on a platform of SPMTs and positioned. It was a precision job, as the SPMT was unable to reverse back up the slope, so to speak.” The job was completed in eight days, working 24 hours a day with a team of 100 people, and the area was reinstated so that traffic could pass over the first two tunnel sections. The east side was next. “The same work, but mirrored. And we had an extra day,” says Gerritsen. “The most nerve-racking moment in this phase was, of course, fitting the third tunnel section. Here too, we couldn’t reverse the SPMT. Fortunately, those ‘concerns’ proved unfounded, as it fitted perfectly.”

Nerve-racking moment
By departing from the reference design, traffic was disrupted for only 3.5 weeks during construction of the underpass. “That is a huge difference from the original method, which would have required a temporary traffic management system for more than a year,” says Vennix. “Of course, this phasing was preceded by an intensive preparation process. This involved informing the local community and stakeholders, as well as reaching holidaymakers and diverting them in good time. The 60-minute delay predicted by our models and communicated to the outside world as a possibility did not occur.” Steenbakkers adds: “All the parties involved deserve great credit. We were a little apprehensive about the impact of partially closing one of the Netherlands’ most important arterial routes in the middle of the summer holidays. But everything went smoothly, and the work was even completed ahead of schedule. Traffic was barely affected. True professionalism.”
Strukton is currently working on completing the underpass and constructing the road pavement. The road will connect to the existing roundabout at GDC Acht business park. This will improve the connection to the A58 slip roads at Best and make the business park less dependent on the A2/N2 alone. The A2/N2 underpass, and with it the completion of the third and final phase of the road infrastructure in Eindhoven Northwest, is expected to be officially opened at the end of September this year.
A business enquiry for Strukton Civiel? Get in touch