Engineering firm helps improve traffic safety and flow with railway underpass
Text Chris ElbersImage Local resident Lammert Duerink

Underpass in use since May 2023
To improve safety and reduce disruption at and around level crossings, WSP has designed a large number of railway underpasses in recent years as part of ProRail’s TunnelAlliantie programme. One of these is the tunnel on Laan van Osseveld in Apeldoorn, a structure finished with Corten steel and green embankments that was completed in May 2023 to replace a level crossing. A challenging and distinctive project, not least because the site is literally on the doorstep of one of WSP’s ten offices in the Netherlands…
As a global provider of engineering and consultancy services in the fields of Transport & Infrastructure, Property & Building, Earth & Environment and Power & Energy, WSP, which has been operating in the Netherlands since 2019, has expertise across a wide range of sectors. The company, recognised by ProRail, specialises in designing civil engineering and building works on and around the railway. Its projects include substations and relay buildings, as well as station refurbishments, platform canopies and NS cycle parking facilities.

A comprehensive approach
WSP has been involved in TunnelAlliantie projects for various clients for five years. The aim is to help resolve major traffic congestion hotspots and unsafe level crossings. According to Jeroen van Dijk, design and team leader for Infrastructure in Nieuwegein, this is made possible by the consultancy and engineering firm’s extensive experience and expertise. “WSP does not just provide advice, it also pays close attention to the practical details of construction methods. We also have knowledge of all the specialist construction techniques involved in building a railway underpass. In addition, our experts are always at the table, which keeps communication lines short and makes it possible to respond quickly. This makes our firm a much sought-after partner for developing civil engineering structures, from tender design through to site engineering.”
“Many underpasses also have an architectural element. For the design of the recently opened underpass in Apeldoorn, developed in collaboration with the architect, Corten steel and expanded metal were chosen as finishes, along with two viewing points, stairways and green embankments. This combination has produced a fantastic visual result.”

A remarkable feat
A defining feature of railway underpass construction is that the section crossing beneath the railway has to be built within a short time frame. For the underpass on Laan van Osseveld, for example, a ‘railway section’ weighing almost 7,000 tonnes was slid into place beneath the tracks using sliding tracks and jacks during a 120-hour possession. A remarkable feat and a good example of how design and construction can come together in practice, says Jeroen. “The design of the concrete structure was coordinated closely with the contractor to accommodate the temporary works required to slide the railway section into place. The project also had an added dimension: the railway underpass is right on the doorstep of our Apeldoorn office. As the contractor operated from our premises during the project, we were close to both the client and the work.”

From level crossing to railway underpass in fifteen months
The new underpass on Laan van Osseveld, a key traffic artery and part of Apeldoorn’s ring road, improves road safety and traffic flow. “The tunnel has two carriageways, each with two lanes, and segregated cycle and pedestrian paths on both sides. Cyclists and pedestrians, who previously crossed the road at the same level, now use a bridge over the tunnel,” says Jeroen of the project, which was completed in approximately fifteen months.
Aannemingsbedrijf Hegeman Bouw & Infra, which delivered the project for ProRail, built the concrete structure beneath the railway entirely in advance on the site to the north of the tracks. The structure was then slid into place in one operation. While it was being built, the concrete structure for the southern approach was constructed on the other side of the tracks, reducing the time required for construction. This approach kept disruption to rail and road traffic and the surrounding area to a minimum.
A business enquiry for WSP? Get in touch
Who worked on it
Spooronderdoorgang Laan van Osseveld in Apeldoorn
- contractorHegeman Bouw & Infra
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSpooronderdoorgang Laan van Osseveld
- ThemeUnderground construction
- SubjectYearbook
- CompanyHegeman Bouw & Infra
- CompanyWSP