Hubertus Tunnel to be upgraded to the Hague Tunnel Standard
Text Roel van Gils Image ICT Group

The 1,600-metre-long Hubertus Tunnel in The Hague has been in operation since 2008. It forms part of the Northern Ring Road and runs from Landscheidingsweg (N440) to Hubertusviaduct (S200). Its control and operating systems are nearing the end of their service life. The Municipality of The Hague has therefore put the renovation out to tender, including a multi-year maintenance contract. The winning bid came from Strukton and ICT Group, who have worked together for many years. ICT Group is upgrading the control and operating systems to the Hague Tunnel Standard as part of this project.
Strukton and ICT Group first worked together on the Koning Willem-Alexandertunnel in Maastricht. “Our contacts have intensified, particularly in recent years. Since 2018, we have also jointly maintained the Hubertus Tunnel,” says Coen van Ommen, project manager at Strukton. “On projects like this, we complement each other perfectly. Our company cultures are also very similar, which makes us such a good match. We are open and transparent with each other.” The two companies are working on the Hubertus Tunnel upgrade from a joint office in Zoetermeer.

Hague Tunnel Standard
Only limited structural work will be carried out on the Hubertus Tunnel. The walls in both tunnel tubes will be repaired and given a dirt-repellent coating. Heat-resistant cladding will also be installed in the enclosed sections of the approach roads, and the tunnel’s asphalt will be replaced. Most of the scope involves replacing or modifying the installations and developing an entirely new control and operating system. “This is the third tunnel in The Hague to receive a control system built in accordance with the Hague Tunnel Standard,” says Marco Plug, consultant at ICT Group. Coen adds: “The Municipality of The Hague has developed a thorough vision for operating the three complex assets in its network, including the Hubertus Tunnel, from a new control centre in Scheveningen in the future. This led to the Hague Tunnel Standard (HTS), a precursor to the National Tunnel Standard (LTS), which was introduced three years later. The HTS includes some installations not found in the LTS, such as air velocity meters and alarm/step-out signs. However, the main difference lies in the distinctive look and feel of the control interface. It differs from the LTS interface and, unlike the Hubertus Tunnel’s current interface, focuses much more on the process of operating the tunnel for traffic, rather than on the technology.”
Smart tools
To allow the renovation to go ahead, the tunnel will be closed completely for nine months from the end of July 2025. “One of the conditions for closing the tunnel is that the software for the entire control and operating system must be delivered with all outstanding issues resolved by then,” says Marco. “We use a range of smart tools to simulate system behaviour digitally. We have carried out a similar exercise before for the Maasdeltatunnel and the Hollandtunnel on the A24 Blankenburg Connection. The initial design phase has now been completed, and the proof of concept has demonstrated how the system works. This provides the basis for the control environment framework. As planned, we will deliver the software in 2025 and then test it. To do so, we are building an integrated test environment that will link the control system to the new installations.”
The aim is to have a fully integrated system, tested with no outstanding test findings, by mid-2025, says Coen. “That gives you greater confidence from the outset that you are going to build a tunnel that works. It is a requirement imposed by The Hague as the client, but it is a very useful one for us as the contractor to meet. After all, this measure removes most integration risks.” Marco adds: “By involving our colleagues in ICT Group’s Managed Services team, who are now also responsible for management and maintenance, in all the key decisions, we are also safeguarding continuity through to the final day of the future maintenance scope.” Coen concludes: “Under the new contract, maintenance is based on total cost of ownership, an approach that involves greater accountability than under the current contract. So it is essential to get it right first time, because then we will benefit from it for fifteen years.”
A business enquiry for Strukton Civiel? Get in touch
Who worked on it
Hubertustunnel in Den Haag, renovation
- contractor
Strukton - operation and controlICT Group
- clientmunicipality of Den Haag
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHubertustunnel
- ThemeUnderground construction
- SubjectDigitalisation & software
- CompanyStrukton Civiel
- CompanyICT Group
- Companymunicipality of Den Haag