The importance of good underground infrastructure for a circular energy network

The importance of good underground infrastructure for a circular energy network

Mijnwater B.V. is building a new network of pipes in Heerlen to supply heating and cooling to homes, offices, shops and industrial businesses. It is a circular energy network that recovers waste heat from the surrounding area and stores surplus heat or cooling for later use. One remarkable feature is that this type of heating and cooling network can save 65 to 90% of energy, in Heerlen and in other cities. A good underground pipe network is essential to making this work.

Mijnwater BV now has 30 professionals on its team to deliver this project. They work in mechanical engineering, urban planning, measurement and control engineering, finance, innovation, civil engineering and infrastructure. The company is growing and is able to expand Heerlen’s existing pipe network to connect new buildings, as well as existing homes, to sustainable energy.

The importance of good underground infrastructure

The Infra department is responsible for installing (shallow) wells, the main pipeline (backbone) and various branches to neighbourhoods and buildings. This is also referred to as installing a cluster network and a sector network. The launch of one of the cluster networks in Heerlen was made possible by the European Heatnet-NWE project (Interreg-NWE).

Preparing and installing an underground pipeline may seem straightforward, but appearances can be deceptive. During construction of the cluster network in Cluster D, project manager Infra Hubert Blom encountered numerous problems. The route crosses a stretch of the Geleenbeek with high natural value, and Heerlen has a rich Roman history. In addition, mining industries of the past left mine spoil and gravel in the ground in several places in Parkstad-Limburg. These are the obstacles that had to be overcome underground. Above ground, traffic diversions were a daily occurrence. Maintaining 24/7 access to the adjoining industrial estates made this quite a feat.

Natura 2000 area

One of the challenges was crossing a Natura 2000 area, where excavation is prohibited. To cross the area, a full-length underground bore had to be made.

Drilling technique

The preliminary design specified HDD (Horizontal Directional Drilling). Drilling techniques for projects and challenges of this kind are now among Mijnwater BV’s standard construction methods. Bidders could distinguish themselves during the tender by varying the depth and length of the bore, as well as its start and end points. As part of the Heatnet-NWE project, we presented the issues to the various bidders during the tender process. The contractors’ proposed solutions were assessed and factored into the award decision.

A perfect end result

The solutions proposed included bores of different lengths and depths, with different start and end points. As the bore forms part of an overall approach, the decision is based not only on the best price: contractors are also awarded points for the quality of their proposals. The contractor awarded the work had designed a bore that was longer than the concept design. This meant the bore could start on a site where disruption to residents and traffic would be significantly reduced. This earned the contractor the most points. When surveying the site after the contract was awarded, the contractor discovered a large concrete culvert beneath the Geleenbeek. A sewer? There was no trace of it on the drawings. Further investigation revealed that a second stream, the Caumerbeek, flows through it. In the past, part of the Caumerbeek had been diverted underground. The bore therefore had to be modified: it had to be deeper and longer still. This meant extra work for us, unfortunately, but the end result was perfect.

Contaminated ground

Mine spoil in the ground

One problem in Parkstad-Limburg is the presence of mine spoil in the ground, a waste product of the former coal industry. The landscape still bears the marks of this in the form of the mountains and hills in Heerlen. They are now covered with a layer of soil and are mostly used as nature reserves and walking areas. But when you start digging, you come across the mine spoil again. It contains various iron compounds and carbon compounds, which means it cannot be used for other purposes. There are several recycling companies in the region with the permits and certification required to accept and process it.

Thorough ground investigation beforehand

Mine spoil is sharp and coarse. This means you cannot simply lay pipes in it, as they would be damaged straight away. Carrying out a ground investigation beforehand makes it easier to estimate the additional costs, since transporting sand to the site and removing the mine spoil is expensive. The mine spoil is taken to specialist processors in the region, who then transport it to a quarry or another mine spoil heap in Brunssum.

Digging up and either reinstating or removing the material is therefore unavoidable. It is essential to map soil contamination in advance and in collaboration with other parties. This allows work to be carried out more efficiently and strategically, and, above all, helps avoid (major financial) risks

Maintaining access for businesses along the route

In addition to underground obstacles, there are also obstacles above ground in this industrial area. Many businesses receive or deliver goods 24/7. Blocking an entrance can quickly cause business losses. This can be taken into account when choosing the route. It may also be possible to block only part of an entrance, then block another part later, or drill beneath a driveway.

Targeted communication with businesses and the municipality

The biggest challenge along the route through this industrial area, between VDL and the new energy cellar, was communicating with the businesses. During the preparation phase, each business was contacted individually, and the municipality was also informed about the pipeline construction and the disruption it would cause. This is a busy road, with many businesses and their entrances and exits, and very little room to work. As the contractor was responsible for the detailed design and construction on this project, responsibility for final coordination and communication with all parties was also assigned to them, working closely with Mijnwater B.V., of course. After the contract was awarded, the contractor completed the detailed design and presented the plans to everyone involved, including the permit authorities and neighbouring businesses. A substantial list of requirements and constraints ensured that a range of measures were used during construction to minimise traffic disruption and maintain access to all businesses. These included drilling beneath driveways, carrying out work on wide driveways in two halves, deploying traffic controllers and diversion routes, working at night and creating temporary entrances at a different location. Mijnwater covers these costs. Businesses and landowners are not normally compensated for disruption, unless pipes are laid on their land. However, if our work causes a business to suffer losses, that is a different matter. Fortunately, Mijnwater was able to prevent this.

naamloos-4-kopieren
Keep communicating with each other

As a route is being constructed, you are always dealing with people and the dynamics within the businesses in the surrounding area. It is therefore advisable to inform the relevant people at those businesses about the upcoming work in advance. This helps prevent them from raising demands afterwards.

Building an infrastructure route through a built-up area is not straightforward. There are many obstacles, and even with thorough preparation and investigation, you can encounter unexpected issues. Project manager Hubert Blom’s recommendations:

  1. Be prepared. Design your route, or better still, carry out an underground survey of the area where you are working. A 3D survey is recommended.
  2. Always be flexible when dealing with businesses or changing your route. Work together and communicate clearly. Make sure you put the right project team together for this. Give the contractor sufficient freedom within the project team.
  3. Always set aside sufficient financial headroom to ensure that you can remain flexible.
  4. Be mindful of the surrounding area, provide information in good time and listen carefully to comments from neighbouring businesses, permit authorities and local residents. Complaints can then be dealt with more quickly and can often be prevented altogether.

Looking to the future

The success of Mijnwater technology is an example for other cities urgently seeking alternatives to natural gas. In principle, the same kind of network could be built in other cities, connecting existing aquifer thermal energy storage (ATES) systems, for example, with the homes in between and with other sources of heat in the city, such as refrigerated supermarkets, data centres and office buildings. This is known as a 5th-generation heating and cooling network (District Heating and Cooling, DHC).

Installing a local circular thermal energy network delivers substantial savings for everyone involved. The major investments are shared, making this an opportunity worth seizing. Setting up this kind of collaboration does, however, require a well-organised coordinating role. Research by CE-Delft and IF-technologie shows that up to 3 million homes in the Netherlands could be disconnected from natural gas using 5GDHC.

In November 2019, Mijnwater B.V. received the ‘grand prize for sustainable infrastructure’ at the Green Solution Awards 2019 ceremony in Paris.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectNews