Tailored engineering for installing sheet piles
Text Suzanne van GaaleImage Kandt BV

Vibration-free installation using a jacking frame
One of the challenges on the Zuidasdok project is logistics. Working space between railway tracks, metro lines, the A10 motorway and the passenger concourses at Amsterdam Zuid station is limited, and disruption to the surrounding area must be kept to a minimum. At Aannemings- en funderingsbedrijf Kandt BV, these are exactly the kinds of logistical and technical challenges they thrive on. Managing director Willem de Meijer explains how they are tackling them on the Zuidas.

Two LeKa piling rigs, three cable cranes. Auxiliary cranes, several hydraulic sheet-piling rigs and a total workforce of 35. This was the deployment of people and equipment during one of the weekends when Kandt BV was hard at work on, among other things, building the new passenger concourse, the Brittenpassage at Amsterdam Zuid station. It is not the numbers, but rather the choice of specialist equipment that characterises the work. “Work on the new Brittenpassage and the existing Minervapassage passenger concourse often takes place in short periods, say a weekend, when we have to work with a large team and specialist equipment in a confined space and within a relatively short timeframe,” Willem explains. “That requires a great deal of coordination with Bouwcombinatie Nieuw-Zuid and a well-prepared work plan. It is bespoke work, exactly where our company excels. We see it as a challenge to find solutions for projects, large and small, with plenty of complications, where design and construction follow closely on one another. That takes flexibility and craftsmanship, which is exactly what makes our work so rewarding.”

Bespoke work specialists
Kandt BV is a family business based in Nieuwerkerk aan de IJssel, with a workforce of around 60. The company started out in earthworks and excavators more than 45 years ago, and soon began building bespoke machines for foundation work. The family business specialises in foundation work, particularly in urban areas where operations have to be carried out in confined spaces. It is brought in for projects involving the supply, installation and, where necessary, removal of anchored or strutted sheet-pile structures, as well as the vibration, driving or drilling of pile structures and LeKa piles. Examples include projects such as A9 BaHo (Badhoevedorp, Holendrecht), the Groningen ring road and A16 Rotterdam. “We design and build a large part of our own equipment fleet, have our own technical service department and also handle transport to the relevant construction sites ourselves. Our hydraulic cranes, for example, are our own design and are specially built for use where space is limited and equipment needs to be set up and dismantled quickly.” For the work at the Zuidas, Kandt BV uses both hydraulic cranes and cable cranes, depending on the length of the sheet pile and how far it needs to be moved into position. In some locations, sheet piles are installed without vibration using a silent piler. “For the new Brittenpassage, for example, we installed a combi wall beneath the deck. As space is limited here, with less than 3 metres of headroom, we cannot use tall cranes. That is why we install the tubes for the combi wall in sections of around 1.80 metres.
They are around 23 metres long in total. We fill the spaces between the tubes with sheet piles to a depth of around 6 metres. The sheet piles are pushed down using hydraulic jacks. Once a section of sheet pile has been pushed down, a new section is fitted, welded using certified welds and jacked down until the required depth is reached.”
Custom-designed jacking frame
As the work on the concourses requires a bespoke approach, Kandt BV has designed and built a special structure. “We developed what is known as a jacking frame for this. We can do that because we have a wide range of materials and attachments in-house, and above all, the expertise.” Speaking of expertise, having the right equipment is not enough without the right people, Willem says. “A good example is drilling through anchors. You use extremely powerful machines for this. It takes a skilled operator, because you need a feel for drilling through the anchors in exactly the right place. I always say: good people make the work.”

Logistics planning
The work at the Zuidas calls for careful logistical planning, Willem says. “Especially when you consider how many passengers pass through Amsterdam Zuid station every day. Add the traffic on the A10 and you are talking about very large numbers. The overall scale is what makes the project interesting and challenging for us. We are involved in preparing and developing a work plan. Our people know their trade, and together we are a team with drive!”
A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch
Who worked on Zuidasdok
- construction consortiumBoskalisMentioned in Striking a balance between minimal disruption, maximum safety and optimal planning
- construction consortium
MobilisMentioned in Striking a balance between minimal disruption, maximum safety and optimal planning - construction consortiumVan GelderMentioned in Striking a balance between minimal disruption, maximum safety and optimal planning
- clientZuidasdokMentioned in Striking a balance between minimal disruption, maximum safety and optimal planning
- demolition workStruijk Sloop- en GrondwerkenMentioned in ‘Circular demolition is a journey we embark on together’
- contractorBouwcombinatie Nieuw-ZuidMentioned in ‘Circular demolition is a journey we embark on together’
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZuidasdok
- ThemeUnderground construction
- SubjectNews
- CompanyKandt Aannemings- en Funderingsbedrijf BV