Stronger together

Vóór en tijdens de realisatie van het gemaal is veel aandacht uitgegaan naar de fasering en logistiek.
Vóór en tijdens de realisatie van het gemaal is veel aandacht uitgegaan naar de fasering en logistiek.

VOBI Infra and Gebr. Beentjes GWW b.v. are essentially the same type of contractors and do much the same kind of work. That gave both contractors a reason to submit a joint tender for the new De Poel pumping station. And it paid off. In December 2019, the contract was awarded to Aannemingscombinatie De Poel. After an intensive construction period, the new pumping station, which regulates water levels in the Waterlandse boezem, was officially opened on 13 April this year. Project manager Bastiaan Blok looks back on the project on behalf of Aannemingscombinatie De Poel.

After an intensive construction period, the new pumping station was officially opened on 13 April this year.

We celebrated winning the tender, of course, by having a slice of cake with HHNK at our first meeting about the project. Then 2020 arrived, says Blok. “After just one in-person progress meeting, the coronavirus pandemic broke out, we went into lockdown and everyone was working from home. The distance to the client suddenly became much greater. Not ideal during the start-up phase of a UAV-gc project. But it showed that people are very adaptable and able to adjust quickly to a new situation.”

Flood protection

The new pumping station replaces the old De Poel pumping station. “The old pumping station had reached the end of its service life and had a lot of defects,” says Blok. “It was a deliberate decision to build the new pumping station in a different location, further along the dyke. There is more space there. That is not only helpful during construction, but also for maintenance.” The entire structure is made of concrete and was built in a series of cofferdams below the waterline. “By choosing a cofferdam with steel sheet piles, we also took over the function of the dyke, ensuring flood protection at all times. The pumping station is founded on precast concrete piles and was built in phases, primarily because the N518 runs through the project site. It is the only road link to the island of Marken. Phased construction also proved to be the most time-efficient way of carrying out the work.”

The new pumping station was built in phases.

Two construction sites

Aannemingscombinatie De Poel began by diverting the N518 so that construction could start on the inlet side. “This side involved the most labour-intensive work, including the concrete structures, mechanical installations, pumps and all the electrical systems that control the pumping station,” Blok explains. “Once the concrete work and the first sections of both (precast) pressure pipelines were complete, we moved the N518 back to its original alignment so that we could build the outlet side. At the same time, we were carrying out finishing work on the inlet side. For a considerable period, we were therefore working on two construction sites at once. This required a lot of coordination. Although this section of the dyke offered the most space available, it was still quite limited for work on this scale.” Blok compares it to building in an urban area. 

Before and during construction of the pumping station, considerable attention was paid to phasing and logistics.

Best for the project

Before and during construction of the pumping station, considerable attention was paid to phasing and logistics. “That was why we appointed our own stakeholder manager, to coordinate effectively with all the direct stakeholders, as well as organisations such as the bus company and the emergency services. We also used speed limits, half-road closures and frequent temporary traffic stops to minimise disruption as far as possible.” Blok looks back on a positive collaboration with all the partners, particularly Hoogheemraadschap Hollands Noorderkwartier. “We faced challenges together and in close consultation, always choosing the ‘best for project’ solution. That is not always how things work out. The result speaks for itself.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectNews
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.