Specialist drilling in truly exceptional conditions
Text Roel van GilsImage Van der Jagt Groep

At the end of 2022, the Prinses Margriettunnel on the A7 between Sneek and Joure made headlines. Several tension piles failed and, under the pressure of the groundwater, one of the tunnel sections rose. “When we read the news in the media, we were already hoping to get a call”, says Adriaan van der Jagt, director of Van der Jagt Groep. And that is exactly what happened. “When a project is large, complex or special, clients in the Netherlands and Belgium know where to find us.”
For 65 years, Van der Jagt Groep has been a versatile specialist, called in by clients for the most challenging demolition and renovation projects. The company is making a real difference on projects including the widening of the A9 between Badhoevedorp and Holendrecht, the Oosterweelverbinding around Antwerp, and now the repair of the Prinses Margriettunnel. “We are restoring the anchoring on this challenging project in a very special way”, says Adriaan. “We feel right at home on projects this complex, because with our different entities we can always come up with a suitable and safe solution.”

Sleeve valve
Extensive investigations in the tunnel revealed that the tunnel floor had become detached from the pile foundations. “To prevent similar problems in the future, it was decided to install new tension anchors beneath the entire tunnel floor, except beneath the aqueduct”, Adriaan explains. “After some trials and consultation with the parties involved, we quickly got to work.” Van der Jagt Groep first drills a hole around 500 mm in diameter, to a depth of 40 centimetres in the tunnel floor. “The hole is then chiselled out and fitted with a sleeve valve by our client, Volker Staal en Funderingen. We then drill through the sleeve, making a hole around 200 mm in diameter and a further 2 metres deep. This takes us below the tunnel floor. We then withdraw the drill and close the sleeve. This prevents groundwater from gushing up through the hole.”

25,000 reinforcing bars
Van der Jagt Groep drills more than 1,050 holes through the tunnel floor in this way, into which Volker Staal en Funderingen installs the new tension anchors. “Before drilling the tension anchors, they inject dämmer through other holes. This liquid clay stabilises the ground beneath the tunnel floor and prevents it from washing away. There are more than 1,000 of those holes too!
First, we drill a hole around 66 mm in diameter, then use a sleeve valve to drill a hole around 40 mm in diameter a further 2 metres deep. That way, we make sure we stay ahead of the two anchor rigs”, says Adriaan. “We follow the contractor’s schedule, as the tunnel remains open to traffic. Once the anchors are in place, we drill another sixteen smaller holes, around 16 mm in diameter, around each 200 mm hole, and insert reinforcing bars into them. These bars are used to ‘tie’ the structure together, connecting the tunnel floor to the anchor head. In total, we drill more than 25,000 of these holes for the bars.”

Special angles
The family business has a team of 15 to 20 employees working on the project at all times. “As well as drilling the holes and bar holes in the tunnel floor, we are also drilling tension anchors into the wing walls at very special angles from a work platform”, Adriaan adds. “We are also carrying out demolition work in the central reservation, because the concrete no longer meets current standards. The viaduct was built shortly after the Second World War, and Rijkswaterstaat is taking the opportunity to carry out life-extending maintenance. We will therefore be scaling up our capacity on the project over the coming months.”

65th anniversary
Van der Jagt Groep celebrated its 65th anniversary in 2023. “That is a milestone in itself”, Adriaan rightly says. “We are a close-knit family business with a motivated team of more than 80 employees. Together, we make a real difference. We specialise in drilling, sawing, demolition and pile breaking on major civil engineering projects. When a project gets serious or complex, people call us. The bigger or more complex the project, the more interesting we find it. We used to be known mainly as an ‘SOS service’, but these days we are brought in as a full-fledged partner at an early stage of a project, so that we can make a difference there too. The repair of the Prinses Margriettunnel is a perfect example.”
A business enquiry for Van der Jagt Groep? Get in touch
Who worked on Prinses Margriettunnel
- clientRijkswaterstaatIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPrinses Margriettunnel
- ThemeUnderground construction
- SubjectNews
- CompanyVan der Jagt Groep
- CompanyRijkswaterstaat