It takes time, diplomacy and technical expertise

Mofverbinding van ondergrondse hoogspanningskabels.
Mofverbinding van ondergrondse hoogspanningskabels.

Thirty parties are rerouting their cables and pipes for ViA15. Everyone can imagine that building a motorway takes a lot of preparation.

But who would have thought that it would take at least a year just to reroute the cables and pipes in the area concerned? It also takes years of experience to manage this process effectively.

For the ViA15 project, VHW Engineering is responsible for managing the cables and pipes process. It has been supporting the GelreGroen contractor consortium in this specialist area of the preparations since the tender stage. Under its ‘Third-party Cables & Pipes’ plan of approach, it ensures that cables and pipes in the area are rerouted in such a way that the motorway can be built and the network operators can then manage them efficiently.

Plan of approach

The ‘Third-party Cables & Pipes’ plan covers the inventory, categorisation and coding of existing cables and pipes; identifying interfaces and constraints for each sub-area/work section; consultation with the network operators and telecoms companies involved; participation in design and phasing meetings; drawing up the final rerouting plans; communication with network operators; process monitoring; and coordinating the actual rerouting of cables and pipes. The work takes time, diplomacy and technical expertise.

Rerouting a water main, including the valve arrangement.

Around thirty stakeholders

The cables and pipes in the project area are managed by no fewer than twelve operators of third-party cables and pipes, as well as eighteen data managers/telecoms providers. VHW Engineering tracked down the relevant contacts at all these organisations and then consulted them about rerouting, modifying and protecting their networks. The formal process then began with a request to modify (VTA) a cable or pipe. Under the applicable legislation and regulations (NKL’99/Telecom Act), they are responsible for part of the rerouting costs, which are set out in a project agreement (POS). 

Diverging interests

“On top of that, all network operators want to provide their customers with the best possible service,” says Henk van Wijlen, senior adviser for Cables and Pipes at VHW Engineering. “Gas suppliers do not want reconnections to take place in winter, when their customers would be left out in the cold. Water companies do not want them to take place in summer, when fresh water is essential. So their interests differ. Our challenge is to help them understand each other, so that we can work towards the best solution.”

“The first rerouting work is now under way on the Hengelderweg for structure 59,” says Hans van Helvoirt, partner at VHW Engineering. “We have been working on it for almost a year, and our dealings with the network operators have gone well.”     

Question about this story? Ask your question

Who worked on ViA15

  1. contractors' joint ventureGelreGroenMentioned in ViA15 project in detail
  2. ground investigationLankelma IngenieursbureauMentioned in Project Via15 | On land, on water and on rail
  3. cable and pipeline processVHW EngineeringIn this story
  4. sister companyDe Vries WerkendamMentioned in 25 years of expertise in foundations and (specialist) anchoring
  5. modular bridgesRetro BridgeMentioned in Eight modular bridges keep the complex ViA15 infrastructure project moving
  6. foundation specialistKandtMentioned in 4.8 kilometres of sheet piling under strict noise and vibration limits

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectViA15
  • SubjectNews
  • CompanyVHW Engineering
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.