IJboulevard: complex civil engineering project in a prime location

On the IJ side of Amsterdam Central Station, Van Hattum en Blankevoort is building IJboulevard, a complex civil engineering project in a prime location. Beneath the water, the IJ will house a bicycle parking facility for 4,000 bikes. Above it, a new part of Amsterdam is taking shape, designed as a public space with a promenade.

The Municipality of Amsterdam wants to keep parked bicycles as far out of sight as possible. The existing floating bicycle parking facility and barges on the IJ side of Amsterdam Central Station are therefore making way for an underground alternative. A highly unusual and, above all, technically complex alternative. The IJ behind Amsterdam Central Station is one of Europe’s busiest waterways. What’s more, the North-South Line also crosses the IJ at this location. According to site manager Rob Gordijn, this is exactly the kind of challenge Van Hattum en Blankevoort is made for.
A puzzle
In the tender, the Municipality of Amsterdam and its Metro and Tram department set strict requirements for movement, partly because of the North-South Line. “The maximum permitted deformation of the existing structures is 6 millimetres, both during construction and later in operation,” says Gordijn. “The North-South Line lies underground, and we are building the bicycle parking facility above it. It needs foundation piles for support, and installing them causes a certain amount of movement. We therefore had to keep that movement within limits. We worked out the solution during the tender stage, and it helped us win the contract. Sustainability was also, naturally, an important factor in the design in terms of the Environmental Cost Indicator (MKI). We also considered how we could add extra functions below the waterline to promote ecology and provide habitat for fish. That also earned us points.”
Pre-construction site
The solution ultimately combines several factors. “One important aspect is that we pre-built the bicycle parking facility in three sections, each approximately 80 by 25 metres, in the Western Harbour Area,” says Gordijn. “This meant we did not need to build a cofferdam on site, and fewer foundation piles were required, 72 TVSI piles in total, thanks to the lighter structure. This considerably reduced the impact on the subsoil, while the lighter structure also resulted in a lower MKI. We were also able to work simultaneously on the foundations at the project site and the permanent concrete structure at the pre-construction site, making the schedule very efficient. Last autumn, the three sections were lowered into place and joined to form one large basin. In the water in front of the sections, we are also building a freestanding vessel impact protection structure to protect the existing quay and bicycle parking facility from potential collisions with the busy shipping traffic on the IJ. Almost all the work and construction logistics are carried out from the water. Road users and local residents are hardly affected by the work, if at all.”
Van Hattum en Blankevoort is currently fitting out the parking facility and building the entrances at ground level. The first signs of paving are also gradually appearing on the 6,000 m2 promenade. Completion is scheduled for the first half of 2023.
Question about this story? Ask your question
Who worked on IJboulevard
- Strukton Immersion Projects
StruktonMentioned in Concrete cycle parking facility transported across the water to the project site - main contractorVan Hattum en BlankevoortMentioned in Concrete cycle parking facility transported across the water to the project site