News

A remarkable project delivered in record time

Text Tony VosImage André Sprong

Het aanbrengen van de verschillende lagen volgt elkaar snel op.
Het aanbrengen van de verschillende lagen volgt elkaar snel op.

Attero appointed Boskalis Nederland as main contractor for the Dak van Drenthe project. Its task was to deliver this wide-ranging project in record time. We speak to manager Olaf Willemse.

Boskalis Nederland is the main contractor on this project. (Image: André Sprong)

Locally, people still often refer to the VAM-berg, named after the Vuil Afvoer Maatschappij, which was founded in 1928. For decades, it transported waste by train from The Hague to Wijster in Drenthe. Over the years, waste disposal has increasingly given way to waste recycling and, now, energy generation. In short, this is a sector that has seen substantial investment in response to environmental regulations.

The entire process was completed in record time.

Highest point

The contract to transform a waste mound into the recreational Dak van Drenthe was awarded to Boskalis, where Olaf Willemse is a manager. Olaf specialises in dry earthworks within the Rivers and Dikes business line. “Boskalis was tasked with covering an 800-metre-long embankment and raising it by 15 metres, creating the highest point in the province,” he says. “A 460-metre-long course with a gradient of 16.4% had to be built on top. The work was complete once the asphalt had been laid. That work took place during the construction industry’s summer holiday so the course could be handed over in early September. Testing followed before the finished course could be opened for the European Cycling Championships.”

Boskalis was awarded one of the two contracts for this project. Olaf says: “Boskalis was awarded the contract to seal the waste mound itself through Attero. The second contract was for building the cycling course on the mound. It was put out to tender by the Province of Drenthe and awarded to Avitec from Nieuw-Buinen.”

Go-ahead

“We were given a tight schedule, from 1 May to 1 September 2023, and the entire project had to be completed in time for the event mentioned above. As soon as Boskalis was given the go-ahead, we began wrapping the mound in bottom ash. An Attero contractor then applied Trisoplast, which provides environmentally friendly stabilisation. Our subcontractor Cofra then rolled out a High Density Poly Ethylene (HDPE) membrane. We laid 30 centimetres of soil on top, followed by a final 80-centimetre layer.”

Boskalis was also responsible for building the cycle paths and the sand and crushed-stone track. Given the short turnaround, work began as soon as provisional permission was granted. Olaf says: “Even when drawing up the schedule during the tender phase, we could see that things would be very tight. There was little time for preparation, which is why we started as soon as possible. We worked long days, and unfortunately our staff on site did not get a summer holiday. Weather is always an uncertain factor on a project like this. For example, laying the membrane was halted for two days because the wind was too strong.”

With an 80 cm cover layer in place, the Dak van Drenthe was ready for the asphalt. (Image: André Sprong)

High output

Olaf says the collaboration with Attero was particularly good: “When you have such a short delivery period, you have to work together. Attero greatly appreciated the way we handled everything. Boskalis’s reputation for delivering quality at a high production rate was one of the reasons we were awarded the contract. Boskalis handled the overall coordination, including that of the various subcontractors and Trisoplast, which works directly for Attero.” 

A business enquiry for Cofra B.V.? Get in touch

Who worked on Dak van Drenthe

  1. main contractorBoskalis NederlandMentioned in Reaching new heights on the Roof of Drenthe
  2. clientAtteroMentioned in Reaching new heights on the Roof of Drenthe
  3. TICC organisationNormec QSMentioned in Independence is paramount

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDak van Drenthe
  • SubjectNews
  • CompanyBoskalis Nederland
  • CompanyCofra B.V.
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.