Construction is under way in Amsterdam Zuidoost on The Ensemble, two ‘skyscrapers’ with 592 rental homes and around 20,000 m2 of space for offices and social, community and commercial facilities. Commissioned by the HeSto joint venture, DISA International solved the complex reinforcement puzzle in the cofferdam, including managing the sinking operation.
The The Ensemble project officially got under way in March 2022. HeSto, a joint venture between Gebr. van ’t Hek and Roel van der Stoel, was commissioned to construct the cofferdam. “This was partly thanks to our previous experience with complex projects involving underwater concrete and sinking reinforcement,” says René Brouwer, manager at Roel van der Stoel. “Given the integrated nature of the cofferdam, we brought together various disciplines at an early stage. Together with our client Cordeel Amsterdam and its structural engineer ABT, we further developed the configuration of the sinking reinforcement, with DISA International contributing its extensive experience in this area.”

Sawing through piles
The cofferdam comprises 140 metres of AZ20-700 sheet piling (permanent) and 170 metres of AZ26-700 sheet piling (temporary), with sheet lengths of 14 metres. The grid also consists of 49 Hek combi piles, diameter 530/650 gi, with an octicon 430 core extending to 26 metres below NAP, and 628 GEWI anchors, diameter 50/200, to around 35 metres below NAP. The cofferdam was initially excavated dry from ground level to around 6.50 metres below NAP. It was then flooded, and the final depth of minus 12 metres NAP was reached using pontoon-mounted equipment. “DISA International’s dive team jet-cleaned the sheet piles, Hek combi piles and GEWI anchors during excavation,” René explains. “Once the clean-up was complete, the dive team used Roel van der Stoel’s upgraded pile and wire saw to cut 290 existing vk40-45 precast piles below the future underwater concrete level and remove them.” A gravel layer was then laid to improve the ground.
Beam grid
“Before we could install the sinking reinforcement, we first placed a 2,500 m2 beam grid underwater in the cofferdam together with HeSto,” says Marc Veldhuizen, dive supervisor at DISA International. “Four beams were also installed in the pedestal for each of the 50 pile caps.” The beams were needed because the sinking reinforcement could not rest directly on the bottom: concrete still had to be placed between them to provide cover, René adds. “This meant the beams had to be positioned very accurately, with a tolerance of 0 to 20 mm.” The sinking reinforcement was in turn largely assembled on site. Dimensional accuracy was also a key consideration here. “Openings had to be made in each cage for the existing piles and GEWI anchors, and these had to be measured out precisely.”

Limited visibility
The sinking reinforcement comprised 148 reinforcement cages for the two towers, ranging in size from around 10 to 15 by 4 metres and weighing approximately 6 to 9 tonnes each. “These cages had to be positioned with great accuracy, with a horizontal tolerance of 0-50 mm,” René explains. “They were stacked in four layers and placed using 200-300 tonne telescopic cranes.” Marc describes it as a complex puzzle. “Sinking reinforcement is routine work for us, but this design was quite challenging, with substantial overlap between the reinforcement. In that respect, it was comparable to our work on the A24 Blankenburgverbinding and the A16 Rotterdam, de Groene Boog. It was a precision job, carried out underwater with visibility of just 30 to 50 centimetres.” Around 850 tonnes of reinforcement was accurately positioned between the piles and GEWI anchors as part of the structure. Around 6,800 m3 of underwater concrete was then poured.
The cofferdam for The Ensemble is now dry. HeSto and DISA International look back on a successful collaboration. “We have successfully completed several projects together in the past, including Valley in Amsterdam and the Piekberging Haarlemmermeer. We are now building a cofferdam together with Roel van der Stoel in the heart of Rotterdam.”
Have a business enquiry for DISA International? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectNews
- CompanyDISA International
- CompanyVeldhuizen b.v.