Renovation, strengthening and widening of the Schipholbrug on the A9
Text David van Goolen (GMICE), Dirk van der Poel en Dirk Feenstra (RC)Image Iv

Work on the Schipholbrug on the A9 is in full swing. The project is being carried out for Rijkswaterstaat and is rightly described as a technical feat. It is a massive infrastructure project. When complete, the bridge will be the widest bascule bridge in the Netherlands. But what exactly is changing?
The Schipholbrug is a major structure on the A9, carrying the road over the Nieuwemeerdijk N231, the Ringvaart and the Schipholdijk. It consists of two bridges, north and south, each with two movable steel leaves and electromechanical operating machinery. The renovation and widening include widening the concrete decks and substructure, renovating the bascule chamber and building a new control building. This bridge structure calls for careful design, planning, construction methods and staging to create a safe, efficient and sustainable bridge that meets growing traffic demand and has a residual service life of 30 years.

Steel decks
The Schipholbrug consists of two sections, one for each direction of travel. Each bridge comprises a western approach span of approximately 85 metres, an eastern approach span of approximately 165 metres and a movable section with a span of approximately 20 metres.
For the new configuration, both existing steel leaves and their drive systems are being completely replaced and widened on both sides. The movable section of the bridge comprises an orthotropic deck supported by cross girders and main girders. The steel leaves of the two bridges, the north and south decks, are almost identical in design and detailing, except for their width, which depends on the number of traffic lanes they need to accommodate. The north deck is significantly wider than the south movable deck.
The ballast tank in the north bridge will contain approximately 442 tonnes of fixed ballast in total. The design of the ballast tank in the south bridge differs slightly from that of the north bridge. The narrower ballast tank in the south bridge will contain approximately 362 tonnes of fixed ballast.

Mechanical equipment
The mechanical equipment of the Schipholbrug is vital to the reliable and continuous operation of the bridge. It comprises a range of components and systems that work together to ensure the bridge can move safely and be maintained effectively.
One of the key elements of the mechanical equipment is the bridge’s operating mechanism. This electromechanical drive allows the bridges to be opened and closed independently to let ships pass. It comprises a robust drive system with electric motors and gearing, using a Panama wheel and pinion drive with a crank and connecting rod, to move the movable sections powerfully and precisely.
The mechanical equipment also includes a crank and connecting rod mechanism that provides a seating force, locking and securing the bridge in its fully closed position. This contributes to the bridge’s safety and minimises the risk of malfunctions.
Sensors and measurement systems are also integrated into the mechanical equipment. These sensors monitor, among other things, the position and speed of the bridge, as well as the forces acting on it. They provide valuable information to the control and monitoring system, enabling the bridge to be positioned accurately and checked for possible deviations during opening and closing cycles. This data allows maintenance to be carried out in good time to ensure the bridge operates optimally.
Other mechanical components include bearings, seals and an emergency drive. Both leaves are also fitted with a manual drive. All these components play a crucial role in the smooth operation of the bridge and must be inspected and maintained regularly to ensure optimal performance.
A holding device is installed in the bascule chamber to secure the bridge in the open position when parts of the drive system need to be maintained or replaced.

Concrete decks
An important aspect of the Schipholbrug’s renovation and widening is widening the existing post-tensioned, cast-in-situ concrete decks. To accommodate the increased capacity requirements resulting from the road widening, the existing concrete decks are being widened and an advanced connection is being created between the existing and new decks. This is being achieved by drilling reinforcement into the existing concrete decks and exposing existing reinforcement by abrasive blasting to install additional reinforcement. This connection ensures that the forces acting on the bridge are distributed evenly across the entire deck. It thus ensures strength, stability and safety, while providing a wider functional carriageway to accommodate the widening.
Bascule chamber
The bascule chamber is an essential part of the Schipholbrug. It plays a crucial role in opening and closing the movable sections of the bridge. The chamber houses the mechanical equipment. It also provides the strength, stability and transfer of forces required during operation of the drive system, which imposes considerable forces on the concrete structures and foundations.
The existing bascule chamber is being renovated and adapted to meet the requirements of the new bridge configuration. Various changes are being made, including replacing the expansion joints, renewing the chamber roof and strengthening the walls and floor. The front wall will also be demolished in its entirety up to approximately 0.5 metres above NAP and rebuilt. These renovation works will ensure that the chamber can withstand the increased loads and forces, and continues to meet structural safety standards for the intended residual service life of 30 years. To accommodate the new bridge configuration and wider roadways, the bascule chamber is being extended on both the north and south sides.
Control building
A new control building is being constructed on the north side of the Schipholbrug. The existing control tower is being demolished in its entirety. The new control building is being built as a ‘box-in-box’ structure. It has been designed to provide a safe and comfortable working environment for the staff who operate the bridge. Although hidden from direct view of road users, the control building has been designed and integrated architecturally, with functionality and aesthetics in mind.
The control building has rounded corners and a range of design features that make it visually distinct from the bridge deck. This will make the building a recognisable feature of the site and contribute to the overall appearance of the bridge.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectBridge construction