Renovation of Nijmegen’s 80-year-old Waalbrug

Renovation of Nijmegen’s 80-year-old Waalbrug

The Waalbrug in Nijmegen is due for renovation. The concrete deck needs replacing, and the steel structure needs to be repaired and strengthened. The bridge layout will be redesigned, and maintenance and painting work will be carried out. The bridge will also get new lighting and railings. All of this is needed to ensure that traffic can continue to cross the bridge smoothly and safely in the future. Contractor consortium Team Waalbrug began the renovation at the end of March, on behalf of Rijkswaterstaat.

Johan van Erk, environmental manager for Team Waalbrug, says: “Team Waalbrug is a Koninklijke VolkerWessels consortium comprising KWS and VolkerRail. Smits Neuchâtel, BKB Infra, Van Straten geleidrail, Westo, Holland Scherm and Vialis are project partners. The team brings together all the knowledge and expertise needed to successfully complete such a challenging job.” 

Special working method
In mid-2018, renovation of the bridge had to be postponed after chromium-6 was found. Additional measures were needed to ensure that the work could be carried out safely for workers, road users, local residents and the environment. Other permits, exemptions, notifications, and work and safety plans were also required. “Now that all of that has been dealt with, we’ve finally got started. The concrete deck is being replaced first. We’ve devised a special working method in which four 9 by 6 metre concrete sections are replaced each week (164 in total). This means the bridge is being completed section by section.”

Waalbrug


A bridge steeped in history
“Renovating a listed bridge is truly special! This historic structure, built in 1936, was partly submerged during the war and partly rebuilt by the German occupiers. The current concrete road deck was installed as part of that work. The combination of concrete and steel on a bridge with such a rich history makes this project enjoyable and unique. As far as possible, its original appearance will be restored. The bridge must remain open during the renovation, both to road traffic and shipping. We’re also working with many different disciplines in a confined space. All in all, it’s a challenging job, and one we’re happy to take on. If we can successfully integrate the repair work that we don’t yet have a full picture of into our working method, and have a high-quality concrete deck in place within the agreed timeframe, we’ll once again be able to bring a project to a proud conclusion,” Johan says. 

Have a business enquiry for KWS? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectWaalbrug
  • ThemeMaterials and techniques for infrastructure
  • SubjectBridge construction
  • CompanyKWS
  • CompanyBKB Infra
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.