Bridge construction

Prinses Amaliabrug and Kogerpolderbrug

Prinses Amaliabrug and Kogerpolderbrug

The Prinses Amaliabrug at West-Knollendam opened to traffic last August. It is the first of two bascule bridges to be replaced as part of the ‘N246-N244 Trajectbenadering’ project. The project involves major maintenance along the entire route between Wormerveer and Alkmaar, improving road safety and traffic flow. The Province of North Holland is the client for the project.

Minimising maintenance and disruption

One of the main requirements for replacing both bridges, the Prinses Amaliabrug and the Kogerpolderbrug, was to minimise maintenance. The Province of North Holland also stipulated that the route alignment must not be changed. This meant that both bridges had to be built in the same locations as the existing bridges, and the road alignment could not be adjusted. Minimising disruption, and limiting and shortening construction work on site as far as possible, was another key factor in the bridge designs.

The bridges comprise two approach spans, a bascule chamber and a steel bascule leaf. The Prinses Amaliabrug has two traffic lanes and a separate cycle path, while the Kogerpolderbrug has three traffic lanes and a separate cycle path. The architectural designs of both bridges are similar in many respects, ensuring that, in line with the visual quality plan, they clearly belong to the same family. A tapered deck and pointed pier heads give the bridges a more slender appearance.

Visual quality plan, Prinses Amaliabrug

Visual quality plan, Kogerpolderbrug

Existing pile foundations

The existing bridges were demolished in their entirety. The existing pile foundations were the only elements not removed, and remained in the ground. Since the new bridges occupy exactly the same positions as the existing ones, designing the new piles was a major challenge. Archive records and as-built drawings were used to map the existing pile layout. The new pile layout was designed around it, with assumed deviations incorporated into a 3D model. The model proved to be highly accurate, so only one pile had to be repositioned during installation, with the new position then verified by calculation.

3D model showing existing piles (grey) and new piles (brown)

The bascule chambers were designed on the assumption that they would be built in cofferdams without underwater concrete, reducing construction time. This results in a relatively shallow chamber, particularly for the Prinses Amaliabrug. Consequently, the counterweight has a short lever arm and had to be made from high-density material (steel billets). This was less of an issue for the Kogerpolderbrug, where the deck is higher, allowing the ballast box to be filled with heavyweight concrete.

The approach spans of the Prinses Amaliabrug are relatively short, making it possible to use solid concrete beams. The Kogerpolderbrug uses box girders. For both bridges, the decks are rigidly connected to the bascule chamber and abutments (wet joints / flexible joints). This eliminates the need for joint profiles that require maintenance.

The piers were built using precast U-shaped units. The units, which have circular openings, were installed over the steel tubular piles on welded brackets. The piles had already been filled with concrete and fitted with starter reinforcement. After the units were positioned, a reinforcement cage was installed for each pier and the units were filled with concrete. This created a structural connection between the piles, precast concrete units and piers. Once the precast deck beams had been installed and the in-situ topping poured, the deck was also structurally connected to the piers. This construction method enabled the piers to be built without cofferdams or dewatering, while minimising disruption to shipping.

The reinforcement was modelled in its entirety using 3D software. At the factory, as much of the reinforcement as possible was assembled into cages and transported to site as complete units. The 3D model and off-site prefabrication resulted in neatly made cages that fitted together well.

Precast pier reinforcement cages being lifted into position

Movable section

The designs for the movable sections of the Kogerpolderbrug and the Prinses Amaliabrug are broadly identical.

Both bridges are driven electromechanically by a crank-and-connecting-rod mechanism. A series-connected drive system was chosen. In broad terms, the arrangement consists of motor and gearbox 1, an intermediate shaft, gearbox 2, a crankshaft, a crank arm, a spring buffer and the bascule leaf. The long intermediate shaft reduces the stiffness of the operating mechanism and limits the forces generated.

To minimise maintenance, the steel bascule leaves were designed as closed, box-shaped steel structures, sealed all around by airtight welding. Closing off the underside reduces the area requiring protective treatment compared with a conventional design with an open underside. The bridges are also easier to maintain thanks to their flat finish. The bottom plates serve not only as practical closure plates, but also act structurally as the bottom flanges of the main girders and cross-girders.

The directly trafficked deck has a ‘standard’ design: the deck plate thickness and weld details comply with NEN-EN 1993-2. The troughs pass through the cross-girders, with the cross-girder webs closely enclosing them. Using continuous troughs allows their legs to be welded continuously to the deck plate over the full length of the deck using an automated welding process.

Two tail girders connect the closed deck structure to the ballast box. The narrow bascule chamber necessitated relatively tight vertical radii in the curves of the tail-girder bottom flanges. The stress increases caused by the curvature were minimised by using thick, narrow flanges.

The design provides a direct load path from the main pivot points to the foundation piles, via continuous columns between the pivot bearings and the chamber floor. To allow the bascule leaf to rotate freely, the main girders are supported on one side only, at their outer edges. The main pivot points are connected by a heavy-duty coupling tube, which prevents the tails between the road deck and ballast box from twisting.

Transported partly at an angle

The bascule leaf for the Amaliabrug was manufactured in Wijhe and then transported along the Zaan to its final location, via the protective-treatment contractor in Amsterdam. During the final leg of the journey, the leaf had to pass under several low bridges and through locks, so it was carried at an angle on the pontoon for the last few kilometres.

The bascule leaf was jacked into place horizontally. Temporary ballast was added to the front of the leaf to allow the bridge to be jacked into position from a pontoon in the main shipping channel, and the ballast box was not filled until after installation. Construction time was minimised by packing the steel ballast billets in crates, which were lifted into the ballast box from the approach span. The leaf was then secured in the open position using the locking mechanism, allowing shipping to pass freely, while work was carried out on the chamber equipment and roof. The Prinses Amaliabrug opened to traffic on 10 August 2019.

Construction of the Kogerpolderbrug is still in full swing. The bridge is expected to be completed in early 2020.

  Prinses Amaliabrug Kogerpolderbrug
Bridge length 71.2 m 87.7 m
Bridge width 15.4 m 21.4 m
Clear navigation width 16.5 m 15.5 m
Bascule leaf length (including ballast box) 27.0 m 26.7 m
Main span length 19.8 m 18.8 m
Structural depth (approx.) 1,200 mm 1,300 mm
Bascule leaf mass (excluding ballast) 238 t 331 t
Ballast weight 205 t 227 t
Design life 100 years 100 years
Traffic class 2 (medium-distance) 2 (medium-distance)
Number of traffic lanes 2 3
Consequence class CC3 CC3

Question about this story? Ask your question

Who worked on it

Prinses Amaliabrug

  1. clientProvince of North Holland

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectPrinses Amaliabrug
  • SubjectBridge construction