Precast wildlife tunnel saves time

To allow small animals to cross the Europaweg safely, the Municipality of Assen decided to build an ecological passage linking Asserbos, Twijfelveld and the Witterveld Natura 2000 site. The wildlife tunnel was completed in a very short time, causing hardly any disruption to traffic.
Traffic experiences little disruption during wildlife tunnel installation

Safety for people and animals
A wildlife tunnel has been built beneath the Europaweg in Assen to link habitats and create ecological connectivity. The tunnel allows small animals, including amphibians, reptiles such as grass snakes, mice, rabbits and foxes, to cross safely and without disturbance. It also reduces collisions with animals, making the road safer for traffic. The tunnel forms part of a wider network of connections.
Ecologist and construction team work together
The Municipality of Assen approached Arcadis to design and install a wildlife tunnel on Assen’s southern ring road. The construction division of the design and consultancy firm Arcadis acted as main contractor for the delivery of this ecological corridor. As the Europaweg has a wide road profile and central reservation, Arcadis’s ecologist first assessed whether ACO’s monolithic wildlife tunnel would be effective enough. Some animals need light in parts of the tunnel, after all. As the enclosed section is no longer than 10 metres, Arcadis’s ecologist concluded that a monolithic wildlife tunnel would be a good solution.

ACO deliberately chose to develop monolithic wildlife tunnels made of polymer concrete. This material has high flexural and tensile strength, meaning that no reinforcement is needed in the concrete. Amphibians and reptiles orient themselves by the Earth’s magnetic field, so reinforcement and other metal products are best avoided in wildlife tunnels. This makes polymer concrete the best available material for wildlife tunnels. It is also non-absorbent, allowing frogs and toads to pass through the ecological corridor without drying out.
Minimal diversion and no disruption to traffic
The Municipality of Assen wanted to minimise disruption to traffic and to schoolchildren travelling by bicycle. It was therefore essential to install the wildlife tunnel during the school holidays. To keep the road closure as short as possible, ACO assembled standard tunnel sections into a ready-to-install, 4-metre-long precast wildlife tunnel.
By supplying the wildlife tunnel as a precast unit, ACO achieved a considerable saving in time. Thanks to careful planning, Arcadis was able to excavate a trench in the road the day before delivery. As the precast concrete foundation had cured properly, Arcadis could install the wildlife tunnel the next day and lay the asphalt the day after that. In total, installation of the ACO Pro Faunatunnel took just three days per carriageway. Because ACO supplied two precast sections for each carriageway, only half of the road was closed at a time. This meant that only a minimal diversion was needed and traffic experienced hardly any disruption. The project was completed on time, so schoolchildren travelling to school were also unaffected.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeMaterials and techniques for infrastructure
- SubjectBridge construction