New ‘brains’ for the Thomassentunnel and the Botlektunnel

New ‘brains’ for the Thomassentunnel and the Botlektunnel may sound a little ‘Frankenstein-like’, but it is nothing of the sort.
Croonwolter&dros is equipping both tunnels with a new PLC platform, developed in collaboration with A-lanes A15 and ABB, with Rijkswaterstaat as the client. The work is part of major maintenance contracts involving A-lanes A15 and Croonwolter&dros.
We speak to Frans Kooijmans, contract manager at A-lanes A15, Robert Heinsbroek, project manager and tunnel technology adviser at Rijkswaterstaat, and Haris Colo, project manager at Croonwolter&dros. Heinsbroek opens the conversation: “The two road tunnels contain a large number of PLCs (Programmable Logic Controllers). These are controlled from the traffic control centre in Rhoon, or from within the tunnel itself. Together with the control software, they form the platform for operating and controlling the tunnels. Croonwolter&dros was tasked with extending the service life of the existing tunnel systems’ control and operating systems, so they can keep going for a few more years, so to speak.”

Old components no longer available new
The PLCs in both tunnels are CPU40 models. “The CPU is a computer and communications module with I/O that communicates with the field equipment. You can think of these CPUs as the brains of the tunnel,” explains Heinsbroek. Colo adds: “ABB was brought in to design the platform, and there was a great deal of consultation. We jointly assessed which components were needed, and found that the CPU40 PLCs in use, which had to be replaced because of their age, were ‘end of service’. They were no longer available, so we had to look for alternatives. That led us to the CPU80. It is a good upgrade, but we needed to assess what it would mean for the existing cables and connections on site. What needed to be modified? What would the work mean for tunnel availability? One major advantage is that the Sattline system, which was already upgraded to version 3.0 in phase 1 of the project, including new PLCs, can continue to be used.” Kooijmans says: “Our aim is to leave all the systems as undisturbed as possible, while ensuring they connect perfectly to the new PLC platform.”

Working together until 2035
Under the project, Croonwolter&dros and A-lanes A15 are working together under a DBFM contract, with Croonwolter&dros as a subcontractor to A-lanes A15. “You really need each other for this work,” says Kooijmans. “We are tied together until the maintenance contract ends in 2035.” The work involves producing the design, manufacturing, carrying out a FAT (Factory Acceptance Test), rolling out and commissioning the system, carrying out a SAT (Site Acceptance Test) and conducting a SIT (Site Integration Test) with the tunnel operator. The operator must say whether they are willing and able to take over the installation, independently of the test report. This is followed by ongoing maintenance.
Heinsbroek concludes: “The work on the tunnels must be carried out in a controlled, properly assured and guaranteed manner, within the specified timeframe. The tunnels were closed for 12 hours at a time during several planned closures. These were full closures in both directions, which required careful planning. It is delicate work, but extremely important. Both tunnels connect the Maasvlakte with Germany.”
A business enquiry for Croonwolter&dros? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectBridge construction
- CompanyCroonwolter&dros