Major maintenance complete: Diemerbrug widened and protected

Major maintenance complete: Diemerbrug widened and protected

Major maintenance on the Diemerbrug has been completed. Commissioned by the Municipality of Diemen, the work has extended the bridge’s service life, improved its functionality and widened the deck to provide a better cycle route. Now that maintenance on the Diemerbrug is complete, similar work can begin on the Venserbrug.

The Diemerbrug is a remotely operated bascule bridge over the Weespertrekvaart, connecting Diemen Centrum with the residential area of Diemen-Zuid. Following its last maintenance works in 2002, the bridge has now been brought fully up to date to ensure it remains in service for years to come. The bridge sections have received a new protective coating, and the barrier cabinets and cameras have been replaced. In addition, the deck has been widened by half a metre on both sides, giving cyclists more room.

Military precision planning

Widening the deck required extensive modifications to the steel structure. It was a complex operation, says Roald van der Slikke, project manager at civil engineering contractor Griekspoor: ‘We carried out all the refurbishment work ourselves. To modify the steelwork, certain sections had to be dismantled, protected against corrosion and reinstalled elsewhere. Meticulous, almost military, planning was essential to ensure everything was back in the right place on time.’

As well as dismantling and reinstalling the steelwork, the team carefully assessed whether the Diemerbrug could withstand such a reconstruction in the first place. ‘We recalculated all the balance loads,’ adds Van der Slikke.

Record pace

Major maintenance on the Diemerbrug was completed in nine weeks, in collaboration with engineering consultancy Westenberg and the Municipality of Diemen. A record pace, according to the project manager: ‘This collaboration played a key role in the project’s success. We were all pulling in the same direction from the outset, which enabled us to get the bridge back into service within nine weeks.’

The same pace will be maintained during the refurbishment of the Venserbrug in Diemen, which will be closed for maintenance from 17 February to 28 March. During this period, traffic will be diverted via the renewed and widened Diemerbrug.

Question about this story? Ask your question

Who worked on it

Diemerbrug in Diemen

  1. civil engineering contractorGriekspoor
  2. engineering consultancyengineering consultancy Westenberg

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDiemerbrug
  • SubjectBridge construction
  • CompanyGriekspoor
  • Companyengineering consultancy Westenberg
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.