Bridge construction

Light and slender thanks to steel

Om de brug op de SPMT’s te kunnen plaatsen, moest deze eerst worden opgevijzeld.
Om de brug op de SPMT’s te kunnen plaatsen, moest deze eerst worden opgevijzeld.

When a bridge is long, elegant and slender, as is the Tegenbosch cycle bridge, it is certain to contain a great deal of steel. After all, no other material is as strong while also being as light and slender as steel. 

The steel elements for the Tegenbosch cycle bridge were engineered, manufactured and installed by CSM Steelstructures. “At 160 metres long and weighing 1,600 tonnes, including 700 tonnes of steel, Tegenbosch was one of our major projects,” says Jules Vankevelaer, project manager at CSM. “The design-and-build team approach was a distinctive feature. The client, Eindhoven municipality, and Dura Vermeer & Ploegam (DV/P) remained involved throughout the project. Together, we came up with the best solutions.”

Mammoet trolleys were used to position the bridge ready for installation.

BIM preparation

CSM first developed the entire bridge in BIM. The model included all the details, such as material divisions, weld preparations and lifting eyes. Vankevelaer: “The BIM model can be used to generate various drawings, which we use to drive production.” The programme also specified how the plates were to be cut, welded together and transported. The individual bridge sections were taken to the site in the largest possible units, where they were assembled into a single structure using numerous temporary supports beneath the arches and deck sections.

Protective coatings

To prevent corrosion, the steel was delivered with a protective coating. At the weld seams, additional paint layers were applied to match the coating system on the rest of the bridge exactly, creating a monolithic finish. The final coat was also treated with an anti-graffiti coating. Should graffiti ever be applied, it can be removed easily using a special procedure. 

The bridge was assembled alongside the motorway.

Blasting on site

Once all the components had been welded together on site, the protective coating had to be reapplied around the weld seams.
“To prevent the blasting grit used during surface preparation from causing a nuisance, we carried out this work, as well as the metallising, inside tents.” Finally, a coat of paint was applied to the entire bridge, once again creating a monolithic finish. This final coat also provides anti-graffiti protection.

Jacking and turning

“The moment the bridge was lifted into position was spectacular,” concludes Vankevelaer. “First, we jacked the bridge up 5 metres so that the trolleys (SPMTs) could be driven underneath it. It took about a week to get the bridge ready for installation. In the end, installation itself took just one night.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeMaterials and techniques for infrastructure
  • SubjectBridge construction
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.