Craftsmanship takes centre stage in N522 Ouderkerk Bridge replacement

Traffic on the N522 in Ouderkerk aan de Amstel crosses the Amstel via Ouderkerk Bridge. Dating from 1936, the bridge needs replacing on both technical and traffic grounds. It will be replaced by two new bridges to improve both road safety and traffic flow on the N522. Combinatie Brug Ouderkerk is responsible for this major replacement project, where age-old craftsmanship takes centre stage.

The existing bridge in Ouderkerk aan de Amstel is an extremely busy crossing, carrying traffic, pedestrians, cyclists and public transport. “There are few alternatives in the village for crossing the Amstel,” says Sander Lodder, branch director at Van Hattum en Blankevoort Regio Noord, which is responsible for the bridge’s concrete work within the consortium. “As well as being in need of replacement on both technical and traffic grounds, the 1936 bridge is a concern for the province of North Holland, which is keen to improve road safety. In the new layout, we’re going from two lanes to three, plus a segregated cycle and footpath.”

A smart concept
The guiding principle in building the new bascule bridge is to minimise disruption to road traffic and shipping. “As a consortium, we came up with a smart concept in which the bascule chamber is built on the riverbank and then slid into place. This means we don’t need to build a cofferdam in the water, which would cause a lengthy closure, and it also limits the need for cranes,” Lodder explains. “The bascule chamber for the first bridge was successfully moved into its final position in the Amstel last summer, using Ct deBoer’s sliding tracks. A major advantage of this method is that we can schedule various tasks in parallel. And, of course, building a chamber on the riverbank is a little more pleasant than doing most of the work underwater. That said, sliding it into place still calls for thorough preparation and expertise, and Ct deBoer is certainly up to the task.”

Two phases
The entire replacement of the old 1936 bridge consists of two phases. “In phase 1, the first bridge is built and opened to traffic, while in phase 2 the existing bridge is demolished and a new one is built on the same site,” says Lodder. “Both bridges are hydraulically operated. Hollandia Infra is supplying the moving steel components, while Vialis is providing the control systems. Last year, KWS Infra completed most of the preparations for the approach road to the first bridge. Traffic is already using part of the new road embankment. This will help ensure a smooth opening of the first bridge. We have experienced some delays, however, because of an incident. As a result, the northern bridge is due to open around the summer this year, after all the systems have been thoroughly tested. Phase 2 will start immediately afterwards. We’ll follow a similar approach, building the bascule chamber on the riverbank and then sliding it into place.”
“From a technical point of view, the replacement is a fairly complex operation, particularly when it comes to carefully coordinating every aspect of the design and construction,” Lodder concludes. “We’ve pooled our construction and design expertise to develop smart solutions, so we can build on the water as efficiently as possible. We’re one of the few civil engineering contractors in the Netherlands that still employs a large number of our own foremen and carpenters. Their knowledge and experience are worth their weight in gold on a technically demanding project like this. No two concrete jobs are the same. There’s also a lot of bricklaying involved. Craftsmanship takes centre stage in the construction of these two new bascule bridges.”
Have a business enquiry for KWS? Get in touch
Who worked on Brug Ouderkerk
- concrete workVan Hattum en BlankevoortIn this story
- sliding tracksCt deBoerIn this story
- moving steel componentsHollandia InfraIn this story
- controlVialisIn this story
- temporary steel structures
Marsé MontageMentioned in Steel temporary works essential for lowering bascule chamber into position - construction consortiumOuderkerk bridge construction consortiumMentioned in Steel temporary works essential for lowering bascule chamber into position
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBrug Ouderkerk
- ThemeSafe working and skilled professionals
- SubjectBridge construction
- CompanyVan Hattum en Blankevoort
- CompanyCt deBoer
- CompanyHollandia Infra
- CompanyVialis
- CompanyKWS