Bus lane in Dichterswijk, Utrecht, requires decisive action

Bus lane in Dichterswijk, Utrecht, requires decisive action

Utrecht is growing, and traffic volumes are increasing. To keep the city accessible in a healthy and attractive way, the municipality wants to make public transport an attractive alternative to the car. The Dichterswijk bus lane is the final link in Utrecht’s major high-quality public transport (HOV) network of dedicated bus lanes.

Multidisciplinary project

silent-piler-kopieren

Installing sheet piles using Silent Piling, by Kandt. (Image: Kandt B.V.)

The existing infrastructure at the site needs to be modified to create a safe traffic environment for all road users, particularly cyclists and pedestrians. The Dichterswijk bus lane is being delivered on behalf of the Municipality of Utrecht by ‘Combinatie Dichterswijk’, comprising KWS Infra and Van Hattum en Blankevoort, both part of VolkerWessels, together with several subcontractors. One of these is Kandt BV, a company with more than forty years’ experience in foundation engineering.

palen-boren-vanaf-water-kopieren

Drilling LeKa piles from the water, by Kandt. (Image: Kandt B.V.)

Tight schedule

Joshua van der Knaap, project manager at Kandt Aannemings- en Funderingsbedrijf BV, explains the work carried out by Kandt on site. “In the first phase, we carried out advance works for the construction of the Expeditiebrug (at Jaarbeurs), which, together with the Nelson Mandelabrug, will cross the new cycle underpass. To extend the Nelson Mandelabrug, we drilled LeKa piles from both land and water. The main challenge was drilling the piles for the central piers from the water, at an inclined angle and close to the existing central piers.” Van der Knaap says it was crucial to schedule everything efficiently within the parameters set by the main contractor, as a road closure was required immediately after phase 1. “That meant working backwards from the deadline, the road closure, using our anticipated production rates to determine when to start our work.” After drilling the piles, Kandt also installed the steel sheet piles, both using low-vibration and vibration-free methods, for the cycle underpass.

o069-20171108-model-onderdoorgang-basis-collage-1e-sceneent_id-kopieren

Dichterswijk bus lane project: a cycle underpass is being built beneath the Nelson Mandelabrug and the Expeditiebrug at Jaarbeurs.
(Image: Combinatie HOV Dichterswijk)

Silent Piling

“From a structural engineering perspective, the sheet piles could only be installed after the piles had been drilled,” Van der Knaap continues. “Some of the sheet piles were pressed into place using Silent Piling. This was necessary to preserve an old quay wall at Villa Jongerius and because the design phase had revealed a utility running parallel to the route. We had limited working space: we were working behind the existing quay wall, so we had to avoid putting too much load on the ground.”

impressie-1-kopieren

Final layout of the Dichterswijk bus lane project: a tree-lined avenue with a bus lane in the middle, flanked by a traffic lane for cars, a two-way cycle path and a footpath on each side. (Image: Combinatie HOV Dichterswijk)

Working from land and water

Because the busy road over the Nelson Mandelabrug had to remain open to motorists during the works, the project site was divided into two sections. Work is being carried out from both land and water. “When you have to meet binding requirements, you adapt your working methods accordingly. Our hydraulic sheet-piling rigs are well suited to the job, and when drilling we took account of peak traffic times when passing beneath the bridge. The navigation opening was also almost as wide as the pontoon needed to ensure the required stability. But thanks to careful preparation, calculations and coordination with the main contractor, we managed to work within the few centimetres of space available on the pontoon. Then there was the road closure I mentioned earlier. As well as good coordination with the main contractor and other subcontractors, this called for flexibility and resilience from our people, and I’m very proud of our team.” Van der Knaap also highlights the open communication and direct lines between the office and the site. He concludes: “This is one of the reasons we are so well equipped to work on large, complex projects of this kind, with several disciplines working at the same time.”    

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on it

Busbaan Dichterswijk in Utrecht

  1. foundation worksKandt

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBusbaan Dichterswijk
  • SubjectBridge construction
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
  • CompanyKWS
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.