A12-Utrechtsebaan overbridge: green gateway to The Hague

Bovenaanzicht van de eindsituatie. In het najaar van 2020 worden de bomen en planten geplant, zodat de overkluizing groen wordt.
Bovenaanzicht van de eindsituatie. In het najaar van 2020 worden de bomen en planten geplant, zodat de overkluizing groen wordt.

By creating nine city gateways, the Municipality of The Hague aims to give residents and visitors a warm welcome in the public spaces of the city.

One of these city gateways is the A12-Utrechtsebaan, an access road being transformed into a ‘Green Gateway’ that puts cyclists and pedestrians, as well as motorists, centre stage. As part of this initiative, an overbridge was recently completed near the Malieveld, better connecting the green spaces of Koekamp and Haagse Bos. Aannemingsbedrijf Gebr. Schouls from Leiden built the sleek, slender structure, with a cycle path and footpath surrounded by dense planting.

Production of a double-curved edge element at Waco.

Gebr. Schouls was awarded the D&C contract on the basis of the Most Economically Advantageous Tender, assessed on best price-quality ratio. The company achieved the maximum score for construction phasing and minimising disruption. Despite severe weather and the challenges posed by the coronavirus pandemic, it successfully completed the overbridge in just five months. Given the varied nature and scale of the work, this can rightly be called a remarkable achievement, agrees project manager Leen van Belen. “The project presented considerable challenges, particularly in terms of scheduling. The overbridge was built in February and March. Landscaping, laying the surfacing and finishing the structure took place from April to June. The design and production phase was already tight, and with the new flora and fauna season approaching, all night-time work also had to be completed before April. On top of that, all work on or above the Utrechtsebaan had to be carried out at weekends because of traffic. In the end, we managed to build the overbridge during the eight weekends when the Utrechtsebaan was closed.”

Green at heart

The structure blends seamlessly into the surrounding ground beside the tunnel. The crossing at the Malietoren over the Utrechtsebaan has been widened by approximately 25 metres compared with the existing viaduct.

At the same time, the structure, assembled from precast concrete elements, has been extensively planted with trees and shrubs, making the overbridge feel like a natural whole to cyclists and pedestrians. “The structure, which stands in a prominent location on a busy route, was built and founded on the existing Utrechtsebaan structure,” Van Belen continues. Existing greenery and future developments were also given careful consideration. “Before work began, we moved the larger existing groups of trees, and the overbridge deck was designed to accommodate future traffic loads. This made it complex to connect the deck elements to one another and to the central support, as they had to be cast together on site.” 

Another impressive feat by Gebr. Schouls was installing the final section of the overbridge. Its size and shape made it impossible to transport this ‘keystone’ to the project site as a single piece. The final section was therefore split into two separate precast elements, which were cast together on a steel frame at the construction site. The massive unit was then lifted into position from the Utrechtsebaan using a
700-tonne crane.

Aerial view of the overbridge under construction. On the left, the edge elements being assembled.

All-round specialist

Since its establishment in 1930, Gebr. Schouls of Leiden has grown into a medium-sized contractor specialising in concrete, road and water engineering. Using skilled employees and modern equipment, the company delivers projects across a range of disciplines. Gebr. Schouls works to traditional RAW specifications, on a Design & Construct basis (with or without the Systems Engineering methodology), and as part of construction teams. This enables the all-round construction specialist to deliver projects from the design stage through to commissioning.

Special precast elements

The precast concrete elements for the overbridge were supplied by Waco of Bergen op Zoom. Waco develops, designs and manufactures structurally sound, architecturally considered products using advanced techniques. This approach keeps work on site to a minimum. 

“The precast elements supplied for the A12-Utrechtsebaan Overbridge project are remarkable in several respects,” says Van Belen. “First, they feature minimal tolerances on the large quantities of reinforcement projecting from the elements, which must align with one another on site. They also have a double-curved form along the edge of the overbridge. They are curved in the horizontal plane and cambered in the vertical plane.”

Have a business enquiry for Waco? Get in touch

Who worked on it

A12-Utrechtsebaan tunnel cover in Den Haag

  1. precast concrete elementsWaco
  2. Construction companyGebr. Schouls

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA12-Utrechtsebaan tunnel cover
  • SubjectBridge construction
  • CompanyWaco
  • CompanyGebr. Schouls