4D Construction Planning Bridges the Gap Between Design and Delivery

Contouren van de Maasdeltatunnel worden zichtbaar aan weerszijde van Nieuwe Waterweg
Contouren van de Maasdeltatunnel worden zichtbaar aan weerszijde van Nieuwe Waterweg

Nobleo Bouw & Infra has been responsible for the complete civil engineering and phasing design for the new Blankenburg connection on behalf of the ‘BAAK’ consortium since the tender phase. At the engineering firm’s recommendation, the immersed tunnel (Maasdeltatunnel) is even being built using 4D Construction Planning, a unique service offered by Nobleo. Linking 3D data to the construction schedule and being able to assess construction methods offer significant benefits, according to Teun Smeijers, head of department at Nobleo Bouw & Infra.

The Blankenburg connection is a complex infrastructure project that started in 2018 and is due for completion in 2024. In the meantime, a new 2×3-lane motorway is being built, running through a cut-and-cover tunnel and an immersed tunnel. Two new interchanges are also being constructed, connecting to the A20 at a lower level and to the A15 at a higher level. “On behalf of BAAK, we are responsible for the civil engineering design for the final situation, among other things, and handle all the main construction phases, as well as the site layout, logistics and construction phasing,” Smeijers explains. “Given the complexity of the project and its many interfaces, we were able to convince the consortium to draw on our ‘4D construction planning’ expertise.”

Virtual and real construction side by side at Maasdeltatunnel Noord.

4D Construction Planning

3D BIM is a good start, but it is used mainly to resolve design interfaces, Smeijers continues. “4D BIM adds the time dimension, but that is not quite enough. With 4D construction planning, we go a step further by assessing construction methods, which allows us to eliminate construction interfaces in advance. This is precisely the stage where things can still go wrong, despite thorough preparations. 4D Construction Planning prevents that. It is also an ongoing process that is continually monitored and adjusted.” Nobleo Bouw & Infra’s 4D construction planning team combines designers and construction planners, bringing together their knowledge of both disciplines. Smeijers says: “We advocate involving construction planning and delivery expertise in the design process at an early stage.” 

4D Construction Planning is a relatively new concept in the infrastructure sector, but according to Smeijers it is already delivering clear benefits.
“As infrastructure projects become more complex, a fully digital connection between design and delivery is becoming essential. It is also an excellent means of communication, both internally and with external stakeholders.”

A business enquiry for Nobleo Bouw & Infra? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectBridge construction
  • CompanyNobleo Bouw & Infra
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.