290 tonnes of steel support structures

Ferross Staalbouw supplied the steel support structures (temporary gallows structures) for the construction of two viaducts (C and D) at the Rozenburg interchange, part of the Blankenburg Connection. “We took responsibility for the engineering, detailed calculations, fabrication, and erection and dismantling of the structures,” says Mark van den Heuvel, Head of Project Management at Ferross Staalbouw. “Over the course of a year and a half, around 290 tonnes of steel will pass through our hands.”
Ferross Staalbouw began the engineering work in November 2019. “Throughout the work, every step is agreed in close and constructive collaboration with BAAK. Everything is discussed down to the finest detail,” says Van den Heuvel. “The added value we offer lies mainly in our extensive expertise in producing, erecting and dismantling the required steel structures. By contributing our thoughts at an early stage, we have arrived at professional, workable solutions to complex challenges.” Ferross is certified to NEN-EN 1090 up to execution class EXC 3. This project is being carried out to EXC 2.

Temporary gallows structure
The superstructure, or the viaduct decks, consists mainly of precast beams. “These beams are not supported by a crossbeam, but by a column strip that will be cast later,” explains Van den Heuvel. “The gallows structure is temporary and supports the beams until the column strip has been cast and cured. Our structure transfers the loads to the foundations.”
Both viaducts are being built in six stages and are approximately 150 metres long and 1.7 metres high, with five spans. “The gallows structure is used at axes 3 and 4. The decks vary in width from 13 to 18 metres and have a
variable longitudinal gradient. According to Van den Heuvel, dismantling is Ferross Staalbouw’s biggest challenge. “Steel components weighing around 8.5 tonnes must be removed. They are located a few dozen centimetres below the top deck. Because of a utility corridor between piers 3 and 4, there is only a few metres of space in which to position lifting equipment for dismantling.”
Reuse
Ferross fabricated, supplied and erected around 199 tonnes of steel for two piers, on axes 3 and 4, of viaduct D. The erection took place in March and April 2020. “Seven lorry loads of steel were delivered for these piers over a period of 3.5 weeks. This steel will be reused for the gallows structure for the two piers of viaduct C. A further 91 tonnes of steel will be added, as these piers are more than 3 metres higher,” adds Van den Heuvel. A quality inspector hired by BAAK also carried out an inspection during the work. The process went smoothly for Ferross, without any delays.

Clients deliberately choose a steel structure. Ferross Staalbouw has all the expertise and craftsmanship needed to develop innovative ideas and turn them into professional designs. Ferross Staalbouw manufactures for government bodies and small and large clients at home and abroad, worldwide. Ferross Staalbouw is a key partner in the metalworking sector.
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeMaterials and techniques for infrastructure
- SubjectBridge construction
- CompanyVan den Heuvel