Vote on privatisation of building control on 14 May

Current building control
The municipality already grants the environmental permit (building permit) if it is satisfied that the paper building plan complies with the technical building regulations. One noteworthy detail: the municipality can also grant the environmental permit if not all the calculations have been submitted.
Research by Vereniging Eigen Huis shows that newly built homes currently have an average of 21 defects at handover. The municipality does not identify these defects because it is not required to check whether the completed building actually complies with the technical building regulations. In the run-up to privatisation, the municipal civil service has been run down for years.
Privatisation
The aim of the proposed Quality Assurance (Building) Act is to improve construction quality. During construction, a private quality assurance provider will monitor the work. They will certify whether the completed building complies with the technical building regulations. Without a positive certificate from the provider, the municipality may refuse permission for the building to be occupied. There will therefore be a mandatory, private final inspection. The municipality will not assess the paper building plan when granting the permit. However, it can take enforcement action following reports from the quality assurance provider.
The debate on 23 April
The Senate debated this privatisation on 23 April. Political parties are deeply divided. All political parties support changes to municipal building control, even if the bill is rejected.
Opponents are largely guided by a gut feeling that building control should remain a government responsibility. In their view, more municipal building control officers should be employed instead of private quality assurance providers.
Minister Ollongren does not want to amend the bill or submit a new one. If the bill is rejected, she believes it is up to the municipalities to improve building control themselves.
The outcome of the vote is uncertain.
Peter de Haan’s view
What matters is that the completed building complies with the regulations, not the paper building plan. A mandatory final inspection is therefore desirable. This inspection can be carried out by a private quality assurance provider or a municipal building control officer.
If the latter model is chosen, many more municipal building control officers will be needed. Opponents of privatisation have no plans for how these additional officers would be funded.
Construction quality must improve. Doing nothing is not an option. It is troubling that the bill is likely to be voted down when there is no fully developed alternative.
Question about this story? Ask your question