Safely exposing water mains with a unique ground-support system

At the invitation of Van Vulpen, we visit its project site in Lexmond. There, two live water mains are being connected. A project that is a perfect fit for Van Vulpen!
Founded in 1966 and based in Gorinchem, Van Vulpen is a true specialist in cable and pipeline projects and trenchless techniques. A look at the Van Vulpen website reveals an impressive collection of films and photos showcasing a range of reference projects. The company’s specialist expertise and professionalism shine through at every turn. That is exactly our first impression when we arrive at the project on Driemolensweg in Lexmond.

Because each sheet pile can be pressed down separately, the system is highly flexible and particularly well suited to use around crossing pipelines or other obstacles.
To expose the water mains safely while taking up as little space as possible, Van Vulpen opted to use a BodemBoX ground-support system. Because the water mains cross the excavation, a damwandBoX was selected. With this BoX system, sheet piles are pressed into a casing. Because each sheet pile can be pressed down separately, the system is highly flexible and particularly well suited to use around crossing pipelines or other obstacles. By leaving the sheet pile raised at the pipeline, the damwandBoX system encloses the pipe on both sides and above. This creates a ground-support structure around the pipeline, allowing work to be carried out safely once the excavation is complete.

Once the water mains had been exposed, a T-piece was fitted to one of them.
The Van Vulpen team is very enthusiastic about the system. This was not their first time using it, so they decided to install it themselves without any instructions. They did so using a 40-tonne long-reach excavator. From experience, they know that the damwandBoX can be installed with a smaller excavator, but a heavier machine with greater reach works much faster and therefore more efficiently. This also improves safety.
Once the water mains had been exposed, a T-piece was fitted to one of them. This is highly specialised work, and the Van Vulpen team is visibly proud of it. “In that respect, ours is a thankless job. We create a real work of art, then it gets covered with soil and no one ever sees it,” one of the Van Vulpen crew says with a laugh. But it is certainly not thankless work: the crew know all too well how essential this connection is to supplying clean drinking water to the surrounding area. “Next week, the mains will be inspected and taken out of service so that we can connect to the other main. The schedule and turnaround time for a connection like this are obviously very important, but we’re on track,” the foreman tells us.

This is highly specialised work, and the Van Vulpen team is visibly proud of it.
The water mains are part of Oase’s water network, and its staff are also at the project site to take samples. If the samples are approved, the Van Vulpen crew can continue installing and connecting the link pipe to complete the connection. Another fine piece of work will then lie underground, unseen, but appreciated by many households.
Question about this story? Ask your question
Keep following this