BouwMat

Reserve pipeline for sewer at a water depth of 66 m

Reserve pipeline for sewer at a water depth of 66 m

As the calculated service life of 50 years is about to be reached, a parallel 4,200 m pressure sewer pipeline needs to be installed…

Since the early 1970s, pressure pipelines for wastewater have been installed in several lakes in Austria. This also applies to Fuschlsee in Salzburg, where a PE sewer pipeline has been in service on the lake bed since 1975. As its calculated service life of 50 years is about to be reached, a parallel pressure sewer pipeline 4,200 m long needs to be installed. It will serve as a reserve pipeline that can be brought into operation immediately if problems arise with the old pipeline. AGRU Kunststofftechnik is supplying the components required for the submarine pressure pipeline, made from high-tech, stress-crack-resistant PE 100-RC.

Submarine pressure pipelines can be installed quickly, and the coastal areas, which are often protected nature reserves, remain undisturbed during pipeline installation. They also require less pipe because the pipelines can be laid in straight lines. As a result, they cost less to build than a pipeline laid on land. However, because a pipeline in deep water is difficult to access if damage occurs, a replacement pipeline must always be available. For this reason, the Fuschlsee-Thalgau wastewater association is investing in a new parallel submarine pressure pipeline made from PE 100-RC. It will run the full length of the crystal-clear mountain lake, whose water is so pure it is drinkable, and carry wastewater from the municipality of Fuschl am See. Between 600 and 900 cubic metres of wastewater will be transported each day from one side of the lake to the other, where it will be routed via a collector to the wastewater treatment plant.

rs16198_img_2596-kopieren

Ing. Erich Peer (second from left) and his son Manuel (far left) were responsible for the installation. Ir. Martin Roither (third from left) planned the submarine pressure pipeline. Christian Winkler (right) is director of the wastewater association.

AGRU Kunststofftechnik had previously supplied 4,248 linear metres of polyethylene pipe with an OD of 280 mm and SDR 17 (16 mm wall thickness, maximum pressure of 10 bar), along with fittings and a CNC-controlled butt fusion machine. The black PE 100-RC pipes, with brown axial stripes to clearly identify their application (wastewater), are highly resistant to point loads and stress cracking. The piping system therefore provides added safety during its decades of service on the stony lake bed at a depth of 66 m, where the temperature remains at just 4°C throughout the year because of water stratification. The material also offers very good resistance to the chemicals found in domestic wastewater, such as alkalis and surfactants.

PEER WASSERBAU GmbH. & Co. KG. is a recognised specialist in hydraulic engineering, building services and civil engineering, and has extensive experience in the professional installation of submarine pressure pipelines. To complete the pressure pipeline, which is more than 4 km long, engineer Erich Peer and his team have a short window of about two months in which to weld together 18-metre-long pipes and then lower them into the pipeline route. The AGRULINE pipes are welded using the AGRU ST CNC 2.0 butt fusion machine. Its latest control technology keeps all parameters, including pressure, temperature and time, under control at all times. The machine records the parameters for every individual weld, and even the welder’s name. Only an experienced, certified welder may make the joints. Because the individual pipe sections are joined using only the pipe material, the result is a monolithic, continuously corrosion-resistant piping system.

rs16236_img_2522-kopieren

The spacing between the weights was calculated so that exactly half of the empty pipe would be submerged.

Weight also plays an important role in submarine pressure pipelines. Concrete weights must prevent the piping system from floating, a problem that can be exacerbated by the possible formation of fermentation gases in the pipeline. The weights also stabilise the pipeline as it rests on the lake bed, ensuring that it remains in the same position for decades to come. PEER uses prefabricated concrete elements made in two halves and placed around the plastic pipe like rings. The halves of each ring are then permanently joined with stainless steel bolts. A foam rubber insert is clamped between the pipe and the concrete to protect the pipe and provide extra security against slipping. These concrete collars, fitted every 3 m, compensate for about 50% of the buoyancy. Once the pipe is filled with water, the concrete weights will cause it to sink to the bottom.

rs16242_img_2529-kopieren

AGRU Kunststofftechnik supplied the pipes, fittings and welding machines for the new submarine pressure pipeline in Fuschlsee.

Around 200 linear metres of ready-to-use pipeline are pushed into the lake from the shore each day. The kilometres-long floating pipeline could drift in the wind, so PEER anchors it every day and tensions it. After about two months of work in all kinds of weather, it is time to lower the 4.2 km pressure pipeline to the lake bed. Several general conditions must be taken into account before this process can begin. It is important to map the lake bed in detail along the pipeline route, and to determine the exact position using GPS coordinates. The lowering process can then begin. The pressure pipeline is carefully filled with lake water at one end and compressed air at the other. The speed at which the pipeline sinks is crucial, as it must not exceed a certain bend angle. The future sewer crosses the entire length of the lake, including its deepest point at 66 m. The entire lowering process therefore takes several hours. After the pipeline has been successfully lowered, the full pressure pipeline is pressure-tested.

The Steinbacher + Steinbacher ZT GMBH office in Thalgau has many years of experience in municipal water engineering and has successfully completed several projects with the Fuschlsee-Thalgau wastewater association. For this reason, Ir. Martin Roither of the Steinbacher office was commissioned to plan the overall concept. This included a feasibility study, planning, tendering and on-site construction supervision for the upstream retention basin, the pumping station and submarine pipeline II through Fuschlsee.

Christian Winkler is director of Reinhalteverband Fuschlsee-Thalgau: “The water in Fuschlsee is of drinking-water quality, and it must stay that way. The new submarine pressure pipeline serves as a reserve and gives us added security, as it can be brought into operation within minutes in an emergency. In consultation with Mr Martin Roither, who handled planning and construction supervision, we therefore also chose a plastic pipeline made from AGRU’s PE 100-RC, as studies have shown that a PE pipeline of this quality can last up to 80 years. We are satisfied with the planning, the delivery and the quality of AGRU’s pipeline. I would also like to thank PEER for the professional and careful installation.”    

Question about this story? Ask your question

Who worked on it

Fuschlsee lake pressure pipeline in Fuschl am See

  1. ir. Martin RoitherSteinbacher + Steinbacher ZT GMBH

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectFuschlsee lake pressure pipeline
  • SubjectBouwMat
  • CompanySteinbacher + Steinbacher ZT GMBH
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.