Privatisation of building control goes ahead

Privatisation of building control goes ahead

On 14 May 2019, the Senate passed the Quality Assurance for Construction Act by a large majority. A bizarre voting result. Both governing parties, CDA and ChristenUnie, voted against this historic construction act. The act privatises building control. It also increases contractors’ liability and duty to warn.

The history of the Quality Assurance for Construction Act

CDA minister Donner drafted the outlines of this construction act in 2011. The CDA subsequently voted in favour in the House of Representatives. As a right-wing party, it is understandable that it would support privatising building control. GroenLinks voted against. In the Senate, the roles were reversed. How can a left-wing party in the Senate vote in favour of privatisation, while a right-wing party seeks to vote down a bill from its own ranks?

On 11 July 2017, the vote on this historic construction act was postponed at the request of former minister Plasterk. CDA senator De Vries-Leggedoor had doubts about the adopted amendments (changes to the legislation) proposed by PvdA MP De Vries. He had charged through like an elephant in a china shop. His amendments increased both the contractor’s liability and their duty to warn. He also introduced additional safeguards for municipalities to enforce the rules during and after construction.

No ‘night of De Vries’

The CDA is very focused on contractors. This is hardly surprising, given that CDA members Elco Brinkman (now a senator) and Maxime Verhagen are the former and current chairs of Bouwend Nederland. Bouwend Nederland is far from enthusiastic about the construction act, which places many responsibilities on contractors. Its criticism is not without reason. Half of construction defects originate in the design of the building plan, which the contractor simply executes. It is no surprise that the CDA voted against the act in 2017.

When the vote was postponed in 2017, neither the CDA nor ChristenUnie was in the governing coalition. Both are now. Since the CDA asked for just six minutes of speaking time before the debate on 23 April 2019, it looked as though the party had changed its mind after all. Over the previous two years, Minister Ollongren had clarified how the adopted amendments would be applied in several letters, hoping to blunt their sharpest edges. The minister also concluded an administrative agreement with the VNG on privatising building control. However, the debate a few weeks ago made it immediately clear that the governing party CDA would vote against. De Vries-Leggedoor began by expressing her appreciation for the minister’s efforts… The rest is history. Alongside the CDA and ChristenUnie, PVV and SP also voted against. No surprises so far.

What is remarkable, however, is that GroenLinks, 50PLUS and Partij voor de Dieren voted in favour. All of them had voted against the bill in the House of Representatives. Together with VVD, D66, PvdA and OSF, this produced 42 votes in favour and 33 against. Still a large majority.

Privatisation of building control

It is better to check the completed building against the technical building regulations than to check the building plan on paper. What matters is that the building itself is safe, not the paper plan. That is why the municipality will no longer check the building plan on paper. Instead, a private quality assurance provider will inspect whether the completed building complies. The municipality may refuse permission to occupy the building without a positive declaration from the provider. At present, the municipality is not required to carry out a final inspection.

Phased privatisation of building control

This privatisation will be introduced in phases. First, the new system will apply to simple buildings such as homes, then to more substantial buildings such as schools, and finally to the largest structures, such as football stadiums. Many parties in the Senate want the new system to apply immediately to more substantial buildings. The minister is right to reject this. It must first be demonstrated that the new system improves construction quality for the lowest-risk buildings. However, the added value of quality assurance providers lies primarily in more complex, larger buildings, which the average municipal building control officer does not deal with every day.

Six months before the new system is due to apply to simple buildings, on 1 January 2021, at the same time as the Environment and Planning Act, the minister will assess whether the construction industry is ready for this change. On 10 May 2019, Minister Ollongren sent the Senate a letter explaining the circumstances in which she would actually privatise building control. This letter helped convince GroenLinks that the new system would not be introduced until after a thorough evaluation.

Municipal enforcement after the new construction act takes effect

The municipality will retain its power to enforce the rules during and after construction. It will be able to enforce the technical building regulations on the basis of information from the quality assurance provider. It will also be able to prevent the building from being occupied. The municipality may do so if the quality assurance provider refuses to confirm that the completed building complies with the technical building regulations.

There is a risk of duplication. The municipality may carry out its own inspections during construction alongside those of the quality assurance provider. This increases the likelihood that municipal charges for obtaining the environmental permit (building permit) will not fall sufficiently. The permit holder will also have to pay the quality assurance provider’s fees. There is a considerable chance that building control costs will therefore rise. For the time being, the minister does not want to force municipalities to reduce their substantial building permit charges. However, total construction costs may still fall if the new system reduces the substantial costs of defects and rework incurred by contractors.

Bouwend Nederland’s objections are justified

The construction act also increases contractors’ liability and duty to warn. Until now, contractors could not be held liable for defects that should have been discovered at handover: hidden defects. Under the new rules, contractors will remain liable after handover unless the defects are not attributable to them. Contractors will also have to warn the client in writing and unambiguously about design errors.

Bouwend Nederland is right to criticise the fact that this places so many responsibilities on contractors. After all, half of construction defects originate in the design, and the contractor has to prove that they made no mistakes. Contractors are likely to take out more expensive liability insurance. Those costs, along with the fees charged by the quality assurance provider, will be passed on to consumers building a home.

At last, serious attention to construction quality

It is positive that the passage of this construction act finally puts construction quality firmly in the spotlight. Research by Vereniging Eigen Huis shows that new-build homes have an average of 21 defects. That figure really must come down.

A mandatory final inspection of the completed building is a positive step, even if it is carried out by a private quality assurance provider.

A separate environmental permit for a construction technical activity under the Environment and Planning Act will also focus attention on construction quality. Coincidentally, Elco Brinkman recently wrote in his memoirs that if he were still a minister, that Environment and Planning Act would never have come about either. The CDA is not keen on change, even when improvements are clearly needed.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectBouwMat
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.