Privatisation of building control goes ahead

On 14 May 2019, the Senate adopted the Quality Assurance for Construction Act by a large majority. The vote produced a bizarre result. Both governing parties, the CDA and the ChristenUnie, voted against this historic construction law. The Act privatises building control. It also increases contractors’ liability and duty to warn.
The history of the Quality Assurance for Construction Act
CDA minister Donner drew up the outline of this construction law in 2011. The CDA subsequently voted in favour in the House of Representatives. As a right-wing party, it is understandable that it would support privatising building control. GroenLinks voted against. In the Senate, the roles were reversed. How can a left-wing party in the Senate vote in favour of privatisation, while a right-wing party wants to vote down a law proposed by its own ranks?
On 11 July 2017, the vote on this historic construction law was postponed at the request of former minister Plasterk. CDA senator De Vries-Leggedoor had doubts about the adopted amendments to the law tabled by PvdA MP De Vries. He had gone about it like a bull in a china shop. His amendments increased both the contractor’s liability and their duty to warn. He also put in place more safeguards enabling the municipality to enforce the rules during and after construction.
No ‘night of De Vries’
The CDA is very focused on contractors. This is hardly surprising, given that CDA members Elco Brinkman, now a senator, and Maxime Verhagen are the former and current chairs of Bouwend Nederland. Bouwend Nederland is far from enthusiastic about the construction law, as it places a great many responsibilities on contractors. This criticism is not without merit. Half of construction defects are in the design of the building plan, which the contractor merely carries out. It is no surprise that the CDA opposed the law in 2017.
When the vote was postponed in 2017, neither the CDA nor the ChristenUnie was in the coalition. They are now. Since the CDA asked for just six minutes of speaking time before the debate on 23 April 2019, it seemed the party had changed its mind after all. Over the past two years, Minister Ollongren had clarified how the adopted amendments would be applied in several letters, hoping to take the edge off them. The minister also reached an administrative agreement with the VNG on privatising building control. However, the debate a few weeks ago made it clear straight away that the governing party CDA would vote against. De Vries-Leggedoor began by expressing her appreciation for the minister’s efforts… The rest is history. The PVV and SP also voted against, alongside the CDA and ChristenUnie. So far, no surprises.
What is remarkable, though, is that GroenLinks, 50PLUS and Partij voor de Dieren voted in favour. They had all voted against the bill in the House of Representatives. Together with the VVD, D66, PvdA and OSF, this produced 42 votes in favour and 33 against. A substantial majority after all.
Privatisation of building control
It is better to check the completed building against the technical building regulations than to check the paper building plan. What matters is that the building itself is safe, not the plan on paper. The municipality will therefore no longer check the paper building plan. Instead, a private quality assurance provider will check that the completed building complies with the regulations. Without a positive declaration from the provider, the municipality may refuse permission to put the building into use. At present, the municipality is not required to carry out a final inspection.
Phased privatisation of building control
Privatisation will be introduced in stages. The new system will first apply to simple buildings such as houses, then to more substantial buildings such as schools, and finally to the largest buildings, such as football stadiums. Many senators want the new system to apply immediately to more substantial buildings. The minister is right not to do so. It must first be demonstrated that the new system improves construction quality for buildings with the lowest risk. That said, quality assurance providers add most value on more complex, substantial projects, which an average municipal building control officer does not deal with every day.
Six months before the new system is due to apply to simple buildings, on 1 January 2021, at the same time as the Environment and Planning Act, the minister will assess whether the construction sector is ready for this change. On 10 May 2019, Minister Ollongren sent the Senate a letter explaining the circumstances in which she would actually privatise building control. That letter helped convince GroenLinks that the new system would only be introduced after a careful evaluation.
Municipal enforcement after the new construction law comes into force
The municipality will, however, retain its power to enforce the rules during and after construction. It can enforce the technical building regulations on the basis of information from the quality assurance provider. It can also prevent the building from being put into use. The municipality may do so if the provider refuses to certify that the completed building complies with the technical building regulations.
There is a risk of duplication. The municipality may carry out inspections during construction alongside the quality assurance provider. This increases the chance that municipal charges for obtaining the environmental permit (building permit) will not fall sufficiently. The permit holder will also have to pay the quality assurance provider’s fees. There is a considerable chance that the cost of building control will therefore rise. For now, the minister does not want to compel municipalities to reduce their substantial building permit fees. However, overall construction costs could still fall if the new system reduces the significant costs of failures incurred by contractors.
Bouwend Nederland’s valid concerns
The construction law also increases contractors’ liability and duty to warn. Until now, contractors could not be held liable for defects that should have been discovered at handover: hidden defects. Under the new law, contractors will remain liable after handover unless the defects are not attributable to them. Contractors will also have to warn the client in writing and unequivocally about design errors.
Bouwend Nederland is right to criticise the fact that this places a great many responsibilities on contractors. After all, half of construction defects originate in the design, and the contractor will have to prove that they made no mistakes. Contractors are likely to take out more expensive liability insurance. Those premiums, together with the cost of the quality assurance provider, will be passed on to the consumer building a home.
At last, serious attention to construction quality
It is positive that the adoption of this construction law has finally brought serious attention to construction quality. Research by Vereniging Eigen Huis shows that newly built homes have an average of 21 defects. That number really must come down.
A mandatory final inspection of the completed building is a positive step, even if it is carried out by a private quality assurance provider.
A separate environmental permit for a building-related technical activity under the Environment and Planning Act will also focus attention on construction quality. Coincidentally, Elco Brinkman recently wrote in his memoirs that if he were still a minister, the Environment and Planning Act would never have been introduced either. The CDA is not keen on change, even when improvements are clearly needed.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.