New premises for Vlissingse Bootliedenwacht

Vlissingse Bootliedenwacht is a service provider in the Port of Vlissingen. Among other things, it is responsible for mooring vessels, towing pontoons and supplying vessels. Construction is currently under way on a new head office with a warehouse, a new loading and unloading jetty, and a modified quay structure. Van der Straaten Aannemingsmaatschappij demonstrated its expertise in foundation engineering and concrete structures at an early stage of the project.
Commissioned by Vlissingse Bootliedenwacht B.V., Van der Straaten Aannemingsmaatschappij is building the concrete substructure for its new office building and warehouse. It consists of precast concrete beams and hollow-core slabs on foundations of precast concrete piles. “We are also repairing the sloping revetment after installing the piles, connecting the existing quay to the new structures, and building a loading and unloading jetty on steel tubular piles, as well as a steel landing with a walkway around the building and access to a floating jetty,” says project manager Matthieu van Damme.

Design and construction team
The substructure design was developed by a design and construction team.
The team comprises Poerstamper Bouw, Vlissingse Bootliedenwacht B.V. and Van der Straaten Aannemingsmaatschappij. Van Damme says: “Over a period of around two years, we assessed various options as part of the team, taking account of safety, sustainability, buildability, cost and construction time. The most suitable option was then developed into a construction design. We were able to contribute our expertise in foundation engineering and concrete structures to mitigate risks, both structural and construction-related, and prepare an optimal bid in terms of cost. As part of the team, we were responsible for carrying out geotechnical investigations on land and water, developing various options, engineering the substructure from outline design through to construction design, coordinating the work with North Sea Port and preparing for the construction phase.”

Van der Straaten Aannemingsmaatschappij is currently driving 83 concrete piles, each 19.5 metres long (square, 450 mm), from a temporary steel platform so that work can proceed independently of the tide.
The building is located entirely alongside the existing quay structure, partly above the existing sloping revetment and partly above the water. According to Van Damme, this presents a particular challenge for the piling work. “The tidal action and the service life of the structure, given its severe exposure class (the structure is entirely in or above salt water), also require extra attention. We are currently driving 83 concrete piles, each 19.5 metres long (square, 450 mm), using our Hitachi CX700 and a D46 pile-driving hammer from a temporary steel platform, enabling us to work independently of the tide. In the meantime, the platform’s steel sheet piles are repositioned and the gaps in the sloping revetment are repaired. Once the piling is complete, we trim the piles to the required height and connect them to the superstructure. A grid of precast concrete beams is placed on the trimmed piles, then topped with hollow-core slabs and a cast-in-situ concrete topping. The topping incorporates the provisions for the superstructure. Once the superstructure has been built, the insulation and floor finish are installed, completing our work on the project.”