Is the CDA killing off the privatisation of building control?

Is the CDA killing off the privatisation of building control?

On 23 April 2019, the Senate will consider the Quality Assurance for Construction Bill, followed by a vote. This landmark building legislation has attracted considerable attention following the terrible fire at Grenfell Tower in London and the collapse of the car park at Eindhoven Airport. Opponents of privatisation fear disasters similar to those in England, where building control is carried out by private-sector bodies. Supporters of privatisation believe that municipal building control failed in Eindhoven.

Status of the Quality Assurance for Construction Bill

Plans to privatise building control were developed more than twenty years ago. The House of Representatives passed the bill by a large majority. At the request of former PvdA minister Plasterk, however, the Senate postponed the vote on 11 July 2017. The CDA has reservations about the PvdA amendments, and without the CDA there is no majority in the Senate. After 658 days, the bill is back for a vote, now with D66 minister Ollongren at the helm. The question is whether the CDA will vote down the bill proposed by coalition partner VVD.

The quality assurance system

First and foremost, the bill does not change the municipality’s enforcement powers. Building control officials can supervise construction work and, where necessary, take enforcement action.

In a debate with the House of Representatives on 6 December 2018, Ollongren said: ‘the framing that building control is being privatised is not correct’. In practice, however, a new private-sector quality assurance provider will have primary responsibility for supervising construction work. That certainly suggests privatisation.

Is this private-sector assessor marking its own homework?

No, the quality assurance provider must be independent of the permit holder, architect and contractor. The provider must declare whether the completed building complies with the building regulations. The building may not be occupied without a positive declaration.

Current municipal building control

Municipalities are not currently required to check whether completed buildings comply with the building regulations. In many cases, they do not. Yet what matters is that the building itself is safe, not just the plans on paper.

At present, the municipality may grant the environmental permit (building permit) if it is merely plausible that the building plans on paper comply with the building regulations. Once the permit has been granted, the permit holder may submit calculations up to three weeks before construction begins.

The choice to improve quality

There are serious concerns about privatisation. Privatisation has a poor reputation in the Netherlands. However, various studies show that smaller municipalities lack the knowledge and expertise needed to provide adequate building control.

Attempts to improve building control have failed time and again. Increasing permit fees to hire more officials is not an option. The fees are already very high. Another possibility is to pool the work within environmental services, allowing officials to share their knowledge and expertise. However, under the Environment and Planning Act, which is due to enter into force on 1 January 2021, building control is not part of the core responsibilities of environmental services.

That leaves the quality assurance system as the remaining option. How can municipalities now hand over building control? The answer is simple: they do not. A municipal environmental permit is still required, and the municipality can still take enforcement action. The only change is that the municipality will no longer check compliance with the building regulations in advance. That is not privatisation. Municipalities will also receive the information they need to enforce the rules. The VNG has agreed this with minister Ollongren.

MOT test for buildings

A private-sector inspection does not necessarily have to go wrong, of course. Think of garages carrying out MOT tests on cars. A mandatory private-sector final inspection is still better than no inspection at all.

Municipalities could of course carry out that final inspection themselves, but unfortunately they do not have the financial resources. Minister Ollongren is also opposed to municipal final inspections, as that would place more responsibility on municipalities. They neither designed nor built the building. It is therefore not primarily the municipality’s job to judge whether it is safe. If a car is involved in an accident shortly after its MOT test because of faulty brakes, the garage that carried out the inspection will be held responsible, at least in people’s minds.

The bill also increases contractors’ liability and imposes a more stringent duty to warn. Bouwend Nederland is among those opposed. More than half of construction defects originate in the design. Contractors must not be made to pay for them.

Now or never

Politicians want to improve building control to prevent accidents such as the one in Eindhoven. The honest answer is that if the Senate votes down the bill, nothing is likely to change for a long time. Minister Ollongren does not want to submit a supplementary bill to the House of Representatives to amend the original bill. No alternative has the support of all parties in the construction sector. Moreover, the construction lobby is very powerful. The bill before the Senate is the compromise that has been reached. Whatever happens, all eyes will soon be on the CDA.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectBouwMat
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.