Innovative. Compact. Sustainable

A new wastewater treatment plant is being built in Weesp. The ICEAS treatment system meets the highest standards, has a compact footprint and uses relatively little energy. This innovative treatment plant will ensure Weesp is ready for the future.
Waterschap Amstel, Gooi en Vecht is having the ICEAS treatment system built on the site of the existing wastewater treatment plant (RWZI) in Weesp. The plant is outdated and, by 2020, will no longer meet the discharge requirements. Waterschap Amstel, Gooi en Vecht tendered the treatment plant under the Uniform Administrative Conditions for Integrated Contracts (UAV-GC) for design & construct, including one year of maintenance. It set out the requirements the plant had to meet and left it to the contractors to develop the best solution.

Treatment tank for the ICEAS treatment process. (Image: Fabion)
Project start-up
“Waterschap Amstel, Gooi en Vecht ultimately chose ICEAS technology,” says Andre Edelenbos, CSO of the Moekotte Groep. “As many parties are involved in delivering a plant like this, the project consortium first organised a project start-up after the contract was awarded. The partners got to know one another better in an informal setting. This was followed by weekly meetings of the core team. The same parties work together and share their expertise to deliver the best plant. The Moekotte Groep is responsible for the electrical installations.”
ICEAS
In the ICEAS treatment system, the entire treatment process, including reaction, settling, decanting and stabilisation, takes place in a single tank. This differs from conventional wastewater treatment plants, where the process is divided between several tanks. The new process saves space and construction costs, creating opportunities for, for example, future expansion. “Weesp’s population has risen sharply in recent years and is expected to keep growing,” says Wolter Wolthers, project manager at the Moekotte Groep. “With the treatment plant’s increased capacity and scope for expansion, Weesp will be ready for the future.”

Visualisation of the treatment plant. (Image: 3Dimensions vof)
Ready to start
The engineering consultancy produced the initial design, which was developed into a final design and then a detailed design for construction. Wolthers says: “The civil engineering contractor could then begin the construction work, while the mechanical engineering contractor installed the equipment. The Moekotte Groep’s main involvement comes when the electrical installations need to be cabled and connected.”
“Every project has its ups and downs, and this one was no exception,” Edelenbos admits. “We had set ourselves a tight schedule. This was only achievable with perfect engineering in the preparatory phase. In practice, you encounter changes that slow the process down. The positive side is that everyone stayed in contact and we worked together to find solutions. All parties always kept the same goal in
sight.”