In recent months, the media have devoted considerable attention to the subject of “failure to honour EMVI commitments”. Promising the earth, the soundness of certain EMVI criteria, enforcement of EMVI commitments and whether it is reasonable to impose fines for failure to honour them: these have all proved to be hot topics. This article offers a brief legal analysis.
The evolution
A clear evolution has taken place in recent years. The original picture of tenderers freely promising the earth, with too little communication between the tender team and the delivery team, has changed. Close collaboration between the tender and delivery teams, coordination meetings with the client, an EMVI checklist, EMVI as a recurring item on every site meeting agenda, and even an EMVI verification app are just some of the features of current practice. This goes hand in hand with clients taking a much stricter approach to EMVI commitments. As quality has become a more prominent aspect of the award criterion, there is growing recognition that EMVI commitments must be enforced. This is necessary, for example, in the interests of the principles of transparency and equal treatment. Checks have also become more rigorous, for instance through the use of EMVI inspection lists. Politicians are taking an interest too. Led by State Secretary Keijzer, there are louder calls for EMVI commitments to be honoured and enforced.
Despite these developments, there are still numerous examples of EMVI commitments going wrong. One notable observation is that making EMVI commitments relating to time and scheduling often also entails a risk.
Case law
Challenging a tenderer’s EMVI commitments in summary proceedings, when a competitor considers them manipulative or unrealistic, remains difficult. See the judgment of the District Court of The Hague of 30 January 2013, ECLI:NL:RBDHA:2013:11066. The main difficulty lies in demonstrating that the EMVI commitments are unrealistic. Further investigation is often not possible in summary proceedings. In a judgment of the District Court of Noord-Holland of 27 July 2016, ECLI:NL:RBNNE:2016:3580, it is notable that the civil court interpreted the EMVI requirements and commitments primarily on the basis of their wording. In a decision of the Arbitration Board for the Building Industry of 30 May 2013, no. 32.994, a project carried out under the UAV-GC involved cables and pipes that differed from the inventory provided by the client. As a result, the contractor had to change the construction method it had committed to in its EMVI commitments. The arbitrators ruled that, under paragraph 3(2) of the UAV-GC, the client was responsible for the accuracy of the information supplied. If that information proves inaccurate, making it impossible for the contractor to carry out its promised construction method, the client is not entitled to impose the associated EMVI penalty. An important tip for tenderers is therefore to address EMVI aspects in deviation forms, as well as financial and time-related matters.
Joost Haest
Severijn Hulshof advocaten