Failure to fulfil MEAT commitments

In recent months, the media have paid considerable attention to the issue of “failure to fulfil MEAT commitments”. Promising the earth, the soundness of certain MEAT criteria, enforcing MEAT commitments and the question of whether penalties for failing to fulfil them are reasonable have all become hot topics. This article provides a brief legal overview.
The evolution
A clear evolution has taken place in recent years. The former picture of tenderers freely promising the earth, with too little coordination between the tender team and the delivery team, has changed. Close cooperation between the tender team and the delivery team, coordination meetings with the client, a MEAT checklist, MEAT as a standing item on the agenda at every construction meeting and even a MEAT verification app are just some of the features of current practice. This picture is closely linked to clients taking a much stricter approach to MEAT commitments. As quality has become a more prominent aspect of the award criterion, it is increasingly recognised that MEAT commitments must be enforced. This is important, for example, in view of the principles of transparency and equal treatment. Checks are also becoming more rigorous, using tools such as MEAT inspection checklists. Politicians are taking an interest, too. Led by State Secretary Keijzer, there are increasingly loud calls for MEAT commitments to be fulfilled and enforced.
Despite these developments, there are still plenty of examples of MEAT commitments going wrong. One notable observation is that making MEAT commitments relating to time and scheduling often entails a risk of its own.
Case law
Challenging a tenderer's MEAT commitments in summary proceedings, on the grounds that a competitor considers them manipulative or unrealistic, remains difficult. See the ruling of the District Court of The Hague of 30 January 2013, ECLI:NL:RBDHA:2013:11066. The main difficulty lies in demonstrating that the MEAT commitments are unrealistic. Further investigation is often not possible in summary proceedings. In a ruling of the District Court of North Holland of 27 July 2016, ECLI:NL:RBNNE:2016:3580, it is notable that the civil court interpreted the MEAT requirements and commitments primarily on the basis of their wording. In a ruling of the Council of Arbitration for the Construction Industry of 30 May 2013, no. 32.994, a project carried out under the UAV-GC involved cables and pipelines that differed from the inventory supplied by the client. As a result, the contractor had to change the construction method it had promised in its MEAT commitments. The arbitrators held that, under paragraph 3(2) of the UAV-GC, the client was responsible for the accuracy of the information supplied. If that information proves incorrect and the contractor can therefore no longer use the construction method it promised, the client is not entitled to impose the associated MEAT penalty. An important tip for tenderers is therefore to address not only financial and time-related aspects in deviation forms, but also MEAT aspects.
Joost Haest
Severijn Hulshof advocaten