Apeldoornseweg: from waste plan to materials plan

How can we maximise sustainability within existing contracts? That was the question facing the municipality of Arnhem when it tackled Apeldoornseweg. “Rather than opting for innovative materials whose value and quality have yet to be proven, we looked at what was possible under the existing RW contracts,” says project manager Sil Polman. “It turned out to be more than we initially thought.” Among other things, the concrete paving slabs and kerbs, concrete sewer pipes and asphalt were reused.
Apeldoornseweg is an important access road into the city and links it to the A12. Redesigning it was no easy task. “The sewer was in a poor state, as was the asphalt. The bus stops were outdated and the traffic lights needed replacing. We also wanted to put an end to flooding. Apeldoornseweg has a change in elevation, so water flows downhill from the adjacent park. We also took the desire for more green space in the city into account. In addition, we listened to local residents: they wanted more crossing points and measures to reduce vehicle speeds.”

With all these challenges, it was already a demanding project. But the team wanted to go a step further on sustainability too. Not by using the project as a test bed for innovative materials, but by choosing products that met existing requirements. “We set a number of sustainability requirements that contractors had to meet. For example, a minimum requirement for the use of secondary aggregate in new concrete products. You can crush material into rubble and use it as a road sub-base. But you can also crush old products into aggregate for new products, or remove products from one location and reuse them elsewhere in their original form.”
Arnhem focused on the latter two forms of reuse. “Not all the sewer pipes and paving slabs could be reused. They were crushed into two different-sized fractions. The coarser fraction was used in new paving slabs and kerbs; the finer fraction was used in the bedding mortar used for the concrete walls behind the kerbs.”
The new concrete kerbs and paving slabs contain 25 per cent secondary aggregate. “As the project progressed, we set a similar requirement for the sewer pipes. In this case, the figure was 15 per cent.” By asking contractors to draw up a materials plan, the municipality kept the dialogue with them going. “Because we kept an open mind, we identified opportunities along the way to make the project even more sustainable.”
Sustainability was important in this project, as was proven quality. “Thanks to the assessment guideline ‘Environmental profiles for concrete infrastructure products’, you can be sure that the percentage of secondary materials is achieved and that the quality of the finished product is up to standard.” More information about the assessment guideline is available at Betonhuis.nl/bestrating/brl.