Guided by the motto ‘smarter connections, better construction’, TBI company Mobilis has been working for over 100 years to improve and optimise infrastructure in the Netherlands and beyond. Mobilis is convinced that better construction starts with smart connections. The best results are achieved in collaboration with partners. A look back at some of the high-profile projects Mobilis contributed to or is still working on over the past year. 

Mobilis is also demonstrating its value in the ‘energy sector’, delivering the foundations for the wintrack pylons on TenneT’s new 48-kilometre, 380 kV high-voltage line.

A16 Rotterdam

The weekend of 5 and 6 March 2022 was a significant milestone in the construction of the A16 Rotterdam. At both ends of the 11-kilometre route, the De Groene Boog consortium, of which Mobilis is a member, made important progress. At the future connection between the A13 and the A16 Rotterdam, the existing A13 towards The Hague was moved to its final alignment beneath a new viaduct. This allowed work to continue safely, without causing additional disruption, on the Netherlands’ first energy-neutral motorway. At the other end of the route, an ever-longer viaduct was slid over live traffic for the first time on the A20/A16 link road. At the Terbregseplein interchange, the viaduct connects the A16 Rotterdam with the existing A16. All in all, it is a complex project that is due to open to traffic in 2024. 

Amstelstroombrug

The Amstelstroombrug over the Duivendrechtsevaart in Amsterdam has already opened, on 31 May 2022 to be precise. The nature-inclusive bridge is characterised by its slender profile and the use of red brick in the underpass and on the pylons. Its original detailing makes reference to Amsterdam’s rich bridge-building tradition, and in particular to the architecture of the Amsterdam School. “The Amstelstroombrug is a fine example of how ecology, the use of sustainable materials and concrete engineering can be elegantly integrated,” says Remco Hoeboer, Managing Director of Mobilis. All the materials used for the Amstelstroombrug are high-quality, sustainable, recyclable and easy to maintain, and will only become more beautiful with time. The bridge can also be adapted if future infrastructure developments call for it.

An ever-longer viaduct was slid over live traffic for the first time on the A20/A16 link road in early 2022.

John Frostbrug

Another ‘bridge project’ was carried out earlier this year in the east of the country. Commissioned by Rijkswaterstaat, the Mobilis–Iris consortium was responsible for major maintenance work on the John Frostbrug in Arnhem. The historic bridge, best known as the iconic landmark of Operation Market Garden, is one of the main road bridges connecting Arnhem city centre across the Lower Rhine to Arnhem-Zuid and the A325. Mobilis was responsible for the concrete work, while Belgian firm Iris Industry Solutions carried out the protective treatment of the steel structures. Innovation and sustainability were key requirements in the tender. The project was a pilot under Rijkswaterstaat’s low-emission construction site programme. The consortium made very limited use of fossil fuels, while also reducing disruption to the surrounding area. This was made possible in part by the e-co2tainer, a mobile unit that can supply green electricity at any construction site. 

RWZI Tilburg

Mobilis’s role as a versatile infrastructure contractor is demonstrated, among other things, by its participation in the Water Zuiveringen Alliantie (WZA), comprising Mobilis, Croonwolter&dros, RWB, TAUW, Sweco and Waterschap De Dommel. Together, they are undertaking the large-scale renovation of RWZI Tilburg. Water quality needs to improve and the installations are due for replacement. The final design (DO) for the aeration tanks has been completed, marking a milestone. Other subprojects are also under way, including modifications to the mechanical treatment system and the process water installation, as well as the replacement of various assets at the wastewater treatment plant under the so-called Long-Term Asset Plan (LTAP). The work will be carried out in eight complex phases to avoid disrupting the process. At the end of September, the final design was presented to the board of Waterschap De Dommel and the full project team. The result will be a robust installation designed with future developments, costs, energy use and the reduction of (nitrous oxide) emissions in mind. Construction is scheduled for 2023-2024.

Commissioned by Rijkswaterstaat, the Mobilis–Iris consortium was responsible for major maintenance work on the John Frostbrug in Arnhem.

SWITCH Zuid-West

Mobilis is also demonstrating its value in the ‘energy sector’. BAM Infra and SWITCH Zuid-West, a consortium comprising Mobilis and Strukton Civiel, are working together to deliver TenneT’s 48-kilometre, 380 kV high-voltage line between Borssele and Rilland. The first new wintrack pylons were installed on foundations built by SWITCH in spring 2022. In the months that followed, the new electricity superhighway became increasingly visible in the municipalities of Reimerswaal and Kapelle, where SWITCH is building the connection. Several pylon sites are already complete or ready for the pylons to be installed, while SWITCH is still busy constructing the foundations at other locations. Once a row of pylons is in place, SPIE Nederland installs the high-voltage lines (conductors). The new high-voltage connection is expected to be completed and commissioned in 2024, after which the existing 150 kV connection will be removed.     

Have a business enquiry for Mobilis? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectYearbook
  • CompanyMobilis
  • CompanyCroonwolter&dros
  • CompanyStrukton Civiel
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.